Loading...
HomeMy WebLinkAbout23A - PROJECT BROADWAY REHABREQUEST FOR COUNCIL ACTION CITY COUNCIL MEETING DATE: DECEMBER 2, 2013 TITLE: CONTINGENCY INCREASE FOR BROADWAY REHABILITATION FROM ANAHURST PLACE TO FIRST STREET (PROJECT NOS. 116736 & 116746) ( CITY MANAGE RECOMMENDED ACTION CLERK OF COUNCIL USE ONLY: APPROVED ❑ As Recommended ❑ As Amended ❑ Ordinance on 1s' Reading ❑ Ordinance on 2ntl Reading ❑ Implementing Resolution ❑ Set Public Hearing For CONTINUED TO FILE NUMBER Increase the contingency for the Broadway Rehabilitation Project by $200,000 which will increase the total construction contract with All American Asphalt, Inc., to $2,967,682. Approve an Appropriation Adjustment recognizing $200,000 in interest earned in the Proposition 1B Fund revenue account and appropriating the same into the Proposition 1B Fund expenditure account DISCUSSION The recommended actions will allow the City to close out and release retention payments to the construction contractor for the Broadway Rehabilitation from Anahurst Place to First Street (Broadway Rehabilitation) Project. This project consisted of reconstructing the pavement, replacing curb and gutter, and repairing sidewalks and curb ramps. At the November 6, 2006, election, California voters passed Prop 1B to allow the state to sell $19.9 billion in general obligation bonds for a variety of transportation priorities for cities and counties, to fund the maintenance and improvement of local transportation facilities. The share of the fund that the City is allocated is determined by the State Controller's Office. Interest has been earned since the inception of the funds, but that amount has not been recognized in prior year Capital Improvement Programs. The recommended appropriation adjustment will recognize the funds in Fiscal Year 2013/2014 and appropriate them for use in the construction of Broadway Rehabilitation Project (Project No. 116746). On July 16, 2012, the City Council awarded a contract to All American Asphalt, Inc., in the amount of $2,443,348. The funding analysis included a 10 percent construction contingency in the amount of $244,334, for a maximum total authorized construction contract expenditure limit of $2,687,682. 23A -1 Contingency Increase Broadway Rehabilitation Project December 2, 2013 Page 2 During construction there were cost savings and other cost efficiencies that resulted in a total cost well below the contract. After evaluation, staff recommended to the City Council the addition of traffic calming bulb -outs at five intersections along the route (Exhibit 1) and upgrades to the antiquated streetlight system along Broadway from McFadden Avenue to Borchard Avenue. On May 6, 2013, the City Council authorized an $80,000 increase in the contract contingency to complete the bulb -outs and streetlight upgrades. While the actual cost of the additional work was $242,212, preliminary estimates projected that there would be some contingency remaining in the construction contract. Therefore, staff requested only what was needed above and beyond the contract authorized limit. Now that project construction and final closeout accounting have been completed, it has been determined that the original contract contingency was needed for the original scope of the project. Therefore, staff is requesting an additional $200,000 to close out the contract. ENVIRONMENTAL IMPACT There is no environmental impact associated with this action. FISCAL IMPACT Proposition 1 B unrecognized interest earnings will be accepted into the Proposition 1 B Fund revenue account (03017002- 50001) and appropriated into the Proposition 1B Fund expenditure account (03017660- 66220, Project No. 116746). Edwin "William' Galvez, P.E. Interim Executive Director Public Works Agency EWG:TC Exhibits: 1. Bulb -out Locations APPROVED AS TO FUNDS AND ACCOUNTS: Francisco Gutierrez _ -- Executive Director Finance & Management Services Agency 23A -2 AND AV hi EDt4GBq AVE *1A ST AVE �::= ANNAF#Mff PL BROADWAY BULB -OUT LOCATIONS SANTA ANA CONTINGENCY INCREASE FOR City Council BROADWAY REHABILITATION PL Agenda Date FROM ANAHURST PLACE TO FIRST STREET 11aL,l December 2, 2013 (PROJECT NOS. 116736 t 116746) 23IBIT 23A -4