Loading...
HomeMy WebLinkAbout23A - PROJ - BROADWAY WATER MAINREQUEST FOR COUNCIL ACTION CITY COUNCIL MEETING DATE: APRIL 15, 2014 TITLE: iNi!Ilk� '. " , , \% CONTINGENCY INCREASE FOR BROADWAY REHABILITATION AND WATER MAIN IMPROVEMENTS FROM CIVIC CENTER DRIVE TO SANTA CLARA AVENUE {PROJECTS 116743 & 1164151 CITY MANAGER RECOMMENDED ACTION CLERK OF COUNCIL USE ONLY: ❑ As Recommended ❑ As Amended ❑ Ordinance on 1" Reading ❑ Ordinance on 2o0 Reading ❑ Implementing Resolution ❑ Set Public Hearing For® CONTINUED TO 0X t10 --m: Increase the contract contingency for the Broadway Rehabilitation and Water Main Improvements Project by $650,000, which increases the Christensen Brothers General Engineering, Inc., construction contract to a maximum of $5,383,144.65. 2. Authorize the City Manager to execute change orders in an amount not to exceed the total authorized contract. DISCUSSION The recommended action will allow the City to cover cost extras anticipated on Broadway north of 171h Street similar to those conditions encountered south of 17th Street. These cost extras are related to underground and pavement conditions on Broadway that were unforeseen. The Broadway Rehabilitation Project consists of upgrades and /or replacement of underground utilities, including the city's water main and water services, followed by street improvements including replacement of curb and gutter, removal and replacement of damaged sidewalks and curb ramps, and reconstruction of the pavement. The work limits on Broadway are between Civic Center Drive and Santa Clara Avenue. On August 5, 2013, the City Council awarded a contract to Christensen Brothers General Engineering, Inc., in the total amount of $4,733,144.65, which included a 10 percent contingency. While potholing the existing utilities in advance of installing the new water main along Broadway, unforeseen concrete pavement was encountered beneath the street, despite coring logs that showed cement treated base at certain locations. Staff also discovered that a sewer trench constructed in the late 1960's was not properly compacted, causing significant voids under the concrete pavement. Consequently, these unforeseen conditions resulted in necessary redesign and additional quantities of asphalt to pave the street. 23A -1 Contingency Increase Broadway Rehabilitation Project April 15, 2014 Page 2 The underground work on Broadway south of 17th Street is nearly completed, and the pavement conditions have been fully revealed. Staff is anticipating similar conditions north of 17th Street and staff therefore recommends making financial preparations to accommodate cost extras without delaying the construction activities. This is critical now that the project is in the second half of the construction phase. ENVIRONMENTAL IMPACT There is no environmental impact associated with this action. FISCAL IMPACT Funding for the increased construction contingency of $650,000 for the Broadway Rehabilitation and Water Main Improvements Project is available as follows: • $200,000 - Traffic Congestion Relief HUT Fund (Account 05917663 - 66220) $450,000 - Water Utility Capital Projects Fund (Account 06617647 - 66301). The Revised Cost Analysis (Exhibit 1) has been adjusted to reflect the total estimated project delivery cost of $5,813,430.65. APPROVED AS TO FUNDS AND ACCOUNTS: G� ' �k� 6c13` .1 Edwin "William" G [Vez, P.E. Francisco Gutierrez Interim Executive Director Executive Director Public Works Agency Finance & Management Services Agency EWG /tc Exhibit: 1. Revised Cost Analysis 23A -2 REVISED COST ANALYSIS PROJECT NOS. 116743 AND 116415 CONTRACT AWARD FOR BROADWAY REHABILITATION AND BROADWAY AND WASHINGTON AVENUE WATER MAIN IMPROVEMENTS Construction Contract (base) $4,302,858.65 Contingency (Original 10 %) $430,286.00 Added Contingency (-15 %) Recommended $650,000.00 $5,383,144.65 Contract Administration $172,114.00 Inspection and Testing $129,086.00 Survey $129,086.00 TOTAL ESTIMATED PROJECT DELIVERY COSTS $5,813,430.65 Exhibit 1 23A -3 23A -4