HomeMy WebLinkAbout23AA - PROJ - FLOWER ST BIKE TRAILREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
OCTOBER 21, 2014
TITLE:
AGREEMENT AMENDMENT FOR
SCULPTURE DESIGN AND INSTALLATION —
FLOWER STREET BIKE TRAIL GAP
CLOSURE PROJECT (NO. 122620)
(STRATEGIC PLAN NO. 5, 5, C)
CITY MANAGER
RECOMMENDED ACTION
CLERK OF COUNCIL USE ONLY:
APPROVED
❑ As Recommended
❑ As Amended
❑ Ordinance on 1" Reading
❑ Ordinance on 2nd Reading
❑ Implementing Resolution
❑ Set Public Hearing For
CONTINUED TO
FILE NUMBER
Approve an addendum to the contract agreement with Green Giant Landscape, Inc., for the
Flower Street Bike Trail Gap Closure Project, to subcontract for the design, fabrication, and
installation of a sculpture for the bike trail Trailhead Plaza at an estimated cost of $87,153.
DISCUSSION
The Flower Street Bike Trail is part of the Golden Loop Recreational Trail, a 24 -mile regional trail
that meanders through the City and provides facilities for biking, jogging, and walking, and is part
of the Orange County Transportation Authority (OCTA) Commuter Bikeways Strategic Plan. It is
also adjacent to local elementary, intermediate, and high schools; South Coast Metro Arts and
Entertainment District; South Coast Plaza; and Metro Pointe Shopping Center (Exhibit 1).
On August 5, 2013, the City Council awarded a $968,500 contract to the lowest responsible
bidder, Green Giant Landscape, Inc., to construct the Flower Street Bike Trail Gap Closure. That
action also approved a contingency of $145,275 to cover any unforeseen construction costs. At
the time, neither the artist nor the sculpture had been selected. However, to avoid the loss of
grant funds, staff recommended moving forward with the construction prior to completing the
selection process.
The approved contract included an allowance to pay for an unnamed artist to be contracted by
the City, and for construction of the sculpture foundation structure. However, the contract also
included a bid item to design, fabricate, and install the unknown art sculpture. Now that the
sculpture and the artist have been determined, the contractor is able to hire the artist directly and
has negotiated the actual cost of the work. Consequently, a separate agreement is required to
handle this unique subcontracting arrangement.
23AA -1
Agreement Amendment for Sculpture Design and Installation —
Flower Street Bike Trail Gap Closure
October 21, 2014
Page 2
Authorized vs. Actual Expenditures
With the exception of the art sculpture work, this project is fully completed. The construction
expenditures for the entire project to date, including contract work and executed change orders,
are $911,574. Staff is recommending a construction contract change order with Green Giant
Landscape, Inc., in the estimated amount of $87,153, to cover contractor and artist costs to
design, fabricate, and install the sculpture (Exhibit 2). The change order cost, which includes the
proposed artwork and all related expenditures, is completely within the framework of the existing
contract and contingency. No additional expenditure authorizations are being sought and no
additional funds are being requested. The project funding is summarized as follows:
EXPENDITURES
Construction Contract
Contingency
Contract
Cost Credits
Cost Extras
SUBTOTAL
RECOMMENDED ADDENDUM
Art Sculpture Change Order
TOTALS
Artwork Selection and Concept
AUTHORIZED
$ 968,500.00
$ 145,275.00
$1,113,775.00
ACTUAL
Recommended
$ 968,500.00
<$102,734.00>
$ 45,807.98
$ 911,573.98
$ 87,153.00
$ 998,726.98
The City received a grant to help build a half -mile of bike trail on the flood control channel property
that runs along Flower Street from MacArthur to Sunflower. The grant includes $80,000 for the
installation of a public art project on the northeast corner of Flower Street and Sunflower Avenue.
Since the property in this area was once owned and farmed by a Japanese- American farmer who
greatly contributed to the growth and prosperity of this region, the artwork will commemorate the
important role of the Japanese- American immigrant agricultural community in Santa Ana.
Last spring, the City partnered with Arts OC and issued a call for artist proposals for this public art
project. Forty -six applications were received. A panel of three art experts working with Arts OC
selected five finalists and asked them to submit renderings and proposals. The five artists
presented their concepts and the committee judged the proposals based on experience,
presentation, concept, and resistance to vandalism. After this process was completed, the selection
committee recommended an untitled piece by artist Richard Turner.
23AA -2
Agreement Amendment for Sculpture Design and Installation —
Flower Street Bike Trail Gap Closure
October 21, 2014
Page 3
The selection committee was comprised of Grace Kook - Anderson, Curator, Laguna Art Museum;
Joseph S. Lewis III, Dean and Professor of Art, Claire Trevor School of the Arts, University of
California, Irvine; and Mike McGee, Gallery Director of the Begovich Gallery, Director of the
Exhibition Design /Museum Studies Program, Associate Professor of Art, California State University,
Fullerton, and a new member of the City's Arts and Culture Commission. City Manager David
Cavazos and Council Member Vince Sarmiento, who represents Ward 1 where the sculpture will be
placed, have also reviewed the committee's recommendation.
On August 21, 2014, the proposed sculpture was presented to the City's Arts and Culture
Commission and they concurred with the selected public art project. The artist, Mr. Richard Turner,
is very well -known and a highly- regarded veteran in the field of public art. The selection committee
was extremely confident in the artist's ability to produce a quality monument that will stand the test
of time. The design pays tribute to the contributions of the Japanese- American farmers while
referencing their Japanese heritage. The work consists of a 7 -foot bronze sculpture of a bunch of
celery, treated with a dark patina with green overtones, and an antique millstone atop a concrete
plinth paved with handpicked stones. The idea of an oversize bunch of celery (one of the primary
mainstays of the Orange County Japanese- American farmers) alludes to the exuberant American
tradition of proclaiming our agricultural abundance. The paved stones evoke the paving of a
pathway in a traditional Japanese garden, while recalling familiar southern California landscaping
styles. The millstone, often used in Japanese gardens, represents the history of food production in
both the East and the West. Together, the piece is minimal in style and straightforward in its
symbolism. Exhibit 3 shows a picture of the small 3 -D model created for the selection process.
STRATEGIC PLAN ALIGNMENT
Approval of this item allows the City to meet Goal #5 Community Health, Livability, Engagement &
Sustainability, Objective #5, Promote a strong arts and culture infrastructure, Strategy C, Promote
arts and culture by partnering with artist groups and merchants to hold events celebrating art in
public plazas, parks and other City - controlled open space.
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the recommended action is exempt
from further review. Categorical Exemptions Environmental Review No. 2006 -197 was filed for
this project. In addition, a Certification of Categorical Exemption and a Statutory Worksheet have
been prepared in accordance with the National Environmental Policy Act.
23AA -3
Agreement Amendment for Sculpture Design and Installation —
Flower Street Bike Trail Gap Closure
October 21, 2014
Page 4
FISCAL IMPACT ,
The estimated total amount needed to deliver the art sculpture is $87,153. Funding to cover all
project costs was approved in the original contract awarded on August 5, 2013, and is available
in the Parks Acquisition and Development Fund (Account No. 31313260 - 66220), Transportation
Enhancement Fund (Account No. 05917660 - 66220), and the Recreational Trail Program Fund
(Account No. 17213240- 66220).
Fred Mousavipour
Executive Director
Public Works Agency
Gerardo Mouet
Executive Director
Parks, Recreation, and Community
Services Agency
FM /EW G /TC
Exhibits: 1. Project Location Map
2. Change Order
3. "Untitled" by Richard Turner
APPROVED AS TO FUNDS AND ACCOUNTS:
Francisco Gutierrez
Executive Director
Finance & Management Services Agency
23AA -4
Description:
Flower Street Bike Trail Gap Closure scope of work included the construction of a 10 -foot wide by
one -half mile long asphalt bicycle trail, landscaping, irrigation, security lighting, wrought iron
fencing and a trailhead plaza, with an art sculpture located at Flower Street and Sunflower Street,
J =I _
MACARTHUR
laza
SUNFLOWER
EXHIBIT 1
ST
saNrn ANA '9 I
PROJECT RPSTPLE 5063 (143) 12 -2620
CITY COUNCIL ?.•
NI A : AGENDA DATe FLOWER STREET BIKE TRAIL GAP CLOSURE
JUNE 3, 2013 SUNFLOWER TO MACARTHUR
" " °"` °." l M1UKI PAGE 1 OF 1
23AA -5
CITY OF SANTA ANA
PUBLIC WORKS AGENCY
CONTRACT CHANGE ORDER
Project Number 12 -2620: Flower Street Bike Trail Gap Closure from Change order Number 3
MacArthur to Sunflower [RPSTPLE 5063 (143)]
To Green Giant Landscape, Inc. Contractor
You are hereby directed to make the herein changes from the plans and specifications or do the folloWng described work not included in the plans and
specifications on this contract.
NOTE: THIS CHANGE ORDER IS NOT EFFECTIVE UNTIL APPROVED BYTHE CITY COUNCILOR CITY MANAGER.
Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time.
Change requested by PUBLIC WORKS AGENCY
EXTRA WORKAT AGREED AND UNIT PRICES
Design and construct the foundation for the art sculpture at the Flower Street Bike Trail
Plaza, as directed per PCO No. 13.
AGREE PRICE $22,325
* The actual costs are based on the actual quantities provided per PCO No. 13.
AGREE UNIT PRICE $4,350
EXTRA WORK AT AGREED NOT TO EXCEED PRICES
5. Design and fabricate an art sculpture at the Flower Street Bike Trail Plaza, per the
attached agreement.
AGREED NOT TO EXCEED PRICE $60,478
f
Page 1 of 2
1 *:4:11 -31111 �a
23AA -6
Description
Oty
Unit Price
Total
2.
Foundation Mock Up*
1
$ 550.00
$ 550.00
3.
Color Option in Foundation *
30
$ 100.00
$ 3,000.00
4.
Grout Bronze Art Sculpture *
8
$ 100.00
$ 800.00
* The actual costs are based on the actual quantities provided per PCO No. 13.
AGREE UNIT PRICE $4,350
EXTRA WORK AT AGREED NOT TO EXCEED PRICES
5. Design and fabricate an art sculpture at the Flower Street Bike Trail Plaza, per the
attached agreement.
AGREED NOT TO EXCEED PRICE $60,478
f
Page 1 of 2
1 *:4:11 -31111 �a
23AA -6
CITY OF SANTA ANA
r.
PUBLIC WORKS AGENCY
CONTRACT CHANGE ORDER
Project Number 12 -2620: Flower Street Bike Trail Gap Closure from Change Order Number 3
MacArthur to Sunflower [RPSTPLE 5063 (143)]
To Green Giant Landscape, Inc. Contractor
You are hereby directed to make the herein changes from the plans and specifications or do the following described work not included in the plans and
specifications on this contract.
NOTE: THIS CHANGE ORDER IS NOT EFFECTIVE UNTIL APPROVED BYTHE CITY COUNCIL OR CITY MANAGER.
Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time.
Change requested by PUBLIC WORKS AGENCY
The compensation both time and cost set forth in this change order comprises the total
compensation due the Contractor, all Subcontractors, and all Suppliers for all work performed per
this change order, including impact on unchanged work. By signing this change order, the
Contractor acknowledges and agrees on behalf of himself, all Subcontractors, and all Suppliers,
that the stipulated compensation includes payment for all work contained in this change order, plus
all payment for interruption of schedules, extended field overhead, home office overhead, profit,
delay, and all impact, ripple effect or cumulative impact on all other work under this Contract. The
signing of this change order constitutes full mutual accord and satisfaction for all changes and
work performed on this project, and that the time and cost paid per this change order constitutes
the total equitable adjustments owed the Contractor, all Subcontractors, and all Suppliers for all
work performed on this project. The Contractor on behalf of himself, all Subcontractors, and all
Suppliers agrees to waive all rights, without exception or reservation of any whatsoever to file any
further claim related to this project.
TOTAL COST THIS CHANGE ORDER: $ _ _ - _ - ESTIMATED $ 87,1 53.00
DECREASE INCREASE
By reason of this order the CONTRACT TIME completion will be adjusted as follows: 224 working days
We the undersigned contractor have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all
equipment, furnish all materials, except as may otherwise be noted above, and perform all service necessary for the work above specified, and will accept as
full payment therefor the prices shown above.
Accepted, Date
By
Approval recommended by
Approved by
Contractor Green Giant Landscape, Inc.
Title
CITYMANAGER
Date
DIRECTOR
Date
Page 2 of 2
23AA -7
ADDENDUM TO AGREEMENT BETWEEN THE CITY OF SANTA ANA AND GREEN
GIANT LANDSCAPE INC.
THIS ADDENDUM TO AGREEMENT is entered into on October 21, 2014, by and
between Green Giant Landscaping, Inc. a California corporation ( "Contractor ") and the City of
Santa Ana, a charter city and municipal corporation organized and existing under the
Constitution and laws of the State of California ( "City ") (collectively "Parties ").
RECITALS:
A. The Parties entered into that certain Agreement 4 12 -2620, dated August 5, 2013, (hereinafter
"said Agreement ") by which Contractor has constructed a portion of the Flower Street Bike
Trail ( "Trail ") between Sunflower Avenue and MacArthur Boulevard.
B. Section 2.19 of said Agreement provided the outline for the erection of a sculpture at the
trailhead plaza area of the Trail. Pursuant to that section the Contractor was to construct the
base upon which the sculpture is to be set and to pick -up, deliver and install the sculpture.
Further, the Contractor was to pay to the artist who constructs the sculpture a sum not to
exceed $60,000.00 for the sculpture and associated works of improvement to the trailhead
plaza.
C. In order to complete the requirements under the Agreement, certain specifications, time -lines
and pay schedules need to be amended and added to the Agreement. The Parties hereto
desire to enter into this Addendum to set forth the additional specifications and to provide
Contractor with the means by which to fulfill its obligations under the Agreement.
WHEREFORE, in consideration of the covenants contained in said Agreement, and
subject to all the terms and conditions of said Agreement, except those as set forth in this
Addendum to Agreement, the Parties agree as follows:
1. Section 1.03 Time of Completion is amended as follows:
The Contractor shall complete all work as amended by this agreement by June 30, 2015.
2. Section 2.19 Trailboa.d Plaza is amended to add the following provisions:
Contractor shall pay to the Artist (Richard Turner) the dollar amounts and at the times as set
forth in the "ARTIST SCOPE OF WORK/FEE SCHEDULE" attached as Exhibit 1 hereto and
incorporated herein. Contractor shall be responsible for obtaining from the Artist and any and
all subcontractors and material suppliers all appropriate lien releases upon payment for said
work/materials.
City shall release to Contractor from the funds allowed in the Agreement the sum of
$60,478.00 upon execution of this Addendum. Contractor agrees that said $60,478.00 is to be
used by Contractor for the sole purpose of paying the Artist the amounts and upon the time
lines as set forth in Exhibit I hereto. Concurrently therewith, City shall reduce the amount of
the performance bond of Contractor on the project to the sum as established in Change Order
No. 3.
The $60,478.00 is a `Not to Exceed' and the Contractor shal l provide invoices for all work
provided by the Artist and all funds not used shall be returned to the City.
23AA -8
The costs to remobilize, design, and constrict the foundation support and install the art
sculpture shall be amended as per Change Order No. 3.
The bid items I 1 and 46 shall be voided and compensation shall be as outlined herein and in
Change Order No. 3.
Further, the City shall take beneficial occupancy all work completed as of August 6, 2014 and
shall pay to Contractor all amounts owed as of August 6, 2014 and shall execute a retention
release for all funds except for 5% of the remaining amounts owed as established in Change
Order No, 3.
3. Except as hereinabove amended, all terms and conditions of said Agreement shall remain in
full force and effect.
IN WITNESS WHEREOF, the parties hereto have executed this Addendum to Agreement on the
date and year first written above.
ATTEST:
MARIA D. HUIZAR
Clerk of the Council
APPROVED AS TO FORM:
SONIA R. CARVALHO
City At ney
By: ,z 2s
fJ h S aka
sistant City Attorney
RECOMMENDED FOR APPROVAL
Fred Mousavipour
`l V Executive Director
Public Works Agency
CITY OF SANTA ANA
David Cavazos
City Manager
Green Giant Landscape, Inc.
Donald L is Henderson
President
Green Giant Landscape, Inc.
EXHIBIT 2 2
23AA -9
Project 12 -2620 Flower Street Bike Trail Plaza Art Sculpture
Artist Scope of Work /Fee Schedule
Foam positive of celery sculpture
Bill Daniels Engraving
Finish on Foam (Estimate) $2,000.00 Due at completion
Deposit to begin work $3,725.00 Due at start
Completion of work $3,725.00 $9,450.00 Due at completion
Bronze celery sculpture and
two bronze plaques
MC3inc
Mounting Pipe and Fill Void (Estimate) $2,000.00 Due at completion
Deposit to begin mold work $3,870.00 Due at start
Begin casting $9,335.00 Due at casting
Complete casting and patina $9,335.00 $24,540,00 Due at completion
Anti - skateboard hardware
Skatestoppers
Begin design development $950.00 Due at start
Begin fabrication $510.00 Due at fabrication
Complete fabrication $510.00 $1,970.00 Due at completion
Millstone
Mil /stones.com
Purchase including shipping $5,700.00 $5,700.00 Due at order
Stone paving
Thompson Building Supplies
Purchase including delivery $1,200.00 Due at order
Installation vendor TBD (Estimate) $3,000.00 $4,200.00 Due at completion
Transportation
Vendors TED (Estimate)
Deliver foam positive to foundry $500.00 Due at delivery
Deliver bronze to site $500.00 Due at delivery
Deliver stone to site $500.00 $1,600.00 Due at delivery
Artist Oversight
Design Development
Construction Oversight
Completion of Installation
Subtotal
General Contractor Markup
Total Not to Exceed
$3,000.00 Due at start
$3,500.00 Due at start
$3,500.00 $10,000.00 Due at completion
$57,360.00
$ 3,118.00
$60,478.00
EXHIBIT 2
23AA -10
Notes on Scope of Work/ Fee Schedule
• Foam positive of celery sculpture: Artist will contract to have the foam positive made for
the celery sculpture. The type of finish depends on what the foundry needs and what kind of
textural detail the Artist wants on the surface; estimate cost for foam positive finish is
$2000.00.
+
Bronze celery sculpture: Artist will contract with foundry to design and fabricate the celery
sculpture. The details for the interior of the sculpture to accommodate the mounting pipe and
the material to fill the interior void will be addressed during design; the estimated cost is
$2,000.00. Artist will contract with foundry to design and fabricate two bronze plaques, one to
recognize City Council and one for the description of the art piece.
• Millstone: Artist will select and purchase the millstone; cost includes shipping.
• Stone paving: Artist will select and purchase the paving stones; cost includes shipping to
the Artist studio. Artist will contract to have the paving stones installed; estimated installation
cost is $3,000.00.
• Transportation: Artist will arrange for the delivery of the foam positive to the foundry, the
bronze celery sculpture to the site, and the paving stones to the site; estimated delivery costs
are $1,500.00.
• Subcontract: Artist to subcontract with Contractor for work and payment identified herein.
Rendering of Art Sculpture
f WN 0 11 :1
23AA -11