HomeMy WebLinkAbout20C - AA - GRAND AVE IMPROVEMENTSREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
AUGUST 4, 2015
TITLE:
INCREASE CONTINGENCY FOR GRAND
AVENUE ROADWAY AND STORM DRAIN
IMPROVEMENTS PROJECT
(PROJECT NOS. 081732 & 126604)
(STR pi EGIC PLAKNOS. 6, 1B, 1C, 1G)
n CA1ss��
CITY MANAGER
CLERK OF COUNCIL USE ONLY:
APPROVED
As Recommended
As Amended
❑ Ordinance on to Reading
❑ Ordinance on a Reading
❑ Implementing Resolution
❑ Set Public Hearing For
CONTINUED TO
FILE NUMBER
1. Increase the contingency for construction of the Grand Avenue Roadway and Storm Drain
Improvements from First Street to Fourth Street by $250,000, which increases the total
estimated construction delivery to $4,183,432.39.
2. Approve an appropriation adjustment to recognize expense reimbursement from Southern
California Edison in the amount of $42,961.27 into the Measure M Street Construction
revenue account and appropriate the funds in the Measure M2 Local Fairshare expenditure
account.
3. Approve an appropriation adjustment to appropriate $50,000 from the Public Works Storm
Drain Construction revenue account to the Public Works Storm Drain Construction
expenditure account.
DISCUSSION
On June 17, 2014, the City Council awarded a contract to Excel Paving Company In the amount
of $3,179,058.24 to construct the Grand Avenue Improvements, Included in the scope of work is
the installation of Class 2 bike lanes, landscaped parkways, sidewalks, bus turnouts, raised
landscaped median, and the relocation of existing utilities along the project, The project also
includes constructing a 78 -Inch storm drain to provide additional drainage capacity to minimize
the potentlal for flooding in this area. The approved total project delivery cost of $3,933,432.39
Includes $367,421 in construction management and inspection costs, as well as a $386,953.15
contingency to cover construction quantity adjustments and miscellaneous cost extras.
During construction of the 78 -inch, 13- foot -deep storm drain, significant unforeseen conditions
were encountered In Grand Avenue from the south side of First Street to the centerline of Fourth
Street. Several utility lines needed to be adjusted and rerouted because they Interfered with the
20C -1
Increase Contingency for Grand Avenue Roadway and
Storm Drain Improvements
August 4, 2015
Page 2
storm drain placement. These utility lines included water and sewer main lines; two, large
communication duct banks; and two, high - pressure gas mains.
Also approved by Council on June 17, 2014, was a $49,000 payment to Southern California
Edison (SCE) to prepare engineering drawings and install the street light poles and lights.
Subsequently, the City began the process to purchase all SCE -owned street lights within the City
limits. Because it would be more expensive to purchase the newly installed street lights back
from SCE, it was determined to be more cost effective for the City to use the engineering
drawings prepared by SCE, purchase the poles and lights, and have the Excel Paving Company
install them with the required conduit. As a result, SCE will be reimbursing the City $42,961.27
for the initial payment less the cost of the engineering work.
Presently, the Grand Avenue project is approximately 68 percent complete. Total amount of the
change orders to date for the utility adjustments and the street light installation is $259,115.41. It
is anticipated that additional change orders will be needed before the project is completed. Job
site conditions have been significantly different from the information provided in the plans,
primarily related to interfering underground utilities associated with the storm drain improvements.
Therefore, staff is recommending a contingency increase of $250,000 to ensure that if
expenditures continue to exceed the Council authorized construction contract amount awarded in
2014, construction may proceed uninterrupted, until completed. With the increased contingency,
the new total delivery cost will be $4,183,432.39, including the construction contract, construction
administration, inspection, testing, and survey (Exhibit 1).
ENVIRONMENTAL IMPACT
There is no environmental impact associated with this action.
STRATEGIC PLAN ALIGNMENT
Approval of this Item supports the City's efforts to meet Goal #6 Community Facilities &
Infrastructure, Objective #1 (establish and maintain a Community Investment Plan for all City
assets), Strategy B (equitably maintain existing streets and associated assets in a state of good
repair so they are clean, safe and aesthetically pleasing for all users), Strategy C (invest
resources and technology to extend the service life of existing infrastructure to protect the City's
investment and support a high quality of life standard), and Strategy G (develop and implement
the City's Capital Improvement Program in coordination with the Community Investment and
Deferred Maintenance Plans
FISCAL IMPACT
$250,000 will be added to the Grand Avenue Roadway and Storm Drain Improvements project
contingency budget for expenditure in Fiscal Year 2015/2016 from the following sources:
20Ci-2
Increase Contingency for Grand Avenue Roadway and
Storm Drain Improvements
August 4, 2015
Page 3
An appropriation adjustment will be prepared to recognize expense reimbursement from
Southern California Edison in the amount of $42;961.27 into the Measure M Street
Construction revenue account (No. 03217002-57000) and appropriate the funds in the
Measure M2 Local Fairshare expenditure account (No. 03217662- 66220) for Project 08 -1732.
2. $157,038.73 in Measure M2 Local Fairshare Funds already appropriated to the project in prior
fiscal years will be reallocated to the project contingency (Account No. 03217662- 66220,
Project 08- 1732).
3. A second appropriation adjustment will appropriate $25,000 from Fund 224 Local Drainage
Area IV revenue account (No. 22417002- 50001) and $25,000 from Fund 225 Local Drainage
Area V revenue account (No. 22517002 - 50001) to the respective expenditure accounts (Nos.
22417660 -66220 and 22517660- 66220) for Project 12 -6604.
J'
re Mousavipour
Executive Director
Public Works Agency
FMIEWG/KW
APPROVED AS TO FUNDS AND ACCOUNTS:
Fro ' isco Gutierr z
Executive Director
Finance & Management Services Agency
Exhibit 1: Cost Analysis
2: Grand Avenue Widening Location Map
3: Request for Council Action dated June 17, 2014
20C -3
20C -4
COST ANALYSIS
INCREASE CONTINGENCY FOR GRAND AVENUE IMPROVEMENTS
AND WIDENING FROM FIRST STREET TO FOURTH STREET AND GRAND
AVENUE STORM DRAIN FROM FIRST STREET TO FOURTH STREET
(PROJECT NOS. 081732 & 126604)
Construction Contract $3,179,058.24
Contract Administration $103,207.00
Inspection and Testing $208,654.00
Survey Staking & Street Light Design $12,599.00
Southern California Edison Reimbursement $42,961.00
Original Contingencies $386,953.15
Increased Contingencies $250,000.00
TOTAL ESTIMATED CONSTRUCTION COSTS $4,183.432.39
Exhibit 1
20C -5
20C -6
4
(NTS)
Z
a
FOURTH STREET
THIRD STREET
1 , ,
i
SECOND STREET
FIRST STREET
LEGEND
PROJECT LIMITS
Exhibit 2
SANTA ANA
.. . -
Lo 410
200-7
20C -8