RESOLUTION NO. 2015 -21
A RESOLUTION OF THE PLANNING COMMISSION OF
THE CITY OF SANTA ANA APPROVING VESTING
TENTATIVE TRACT MAP NO. 2015 -01 AS CONDITIONED
TO ALLOW A SUBDIVISION FOR INDIVIDUAL LOTS FOR
SINGLE FAMILY RESIDENCES FOR THE PROPERTY
LOCATED AT 520 SOUTH HARBOR BOULEVARD
BE IT RESOLVED BY THE PLANNING COMMISSION OF THE CITY OF
SANTA ANA AS FOLLOWS:
Section 1. The Planning Commission of the City of Santa Ana hereby finds,
determines and declares as follows:
A. Applicant is requesting approval of Vesting Tentative Tract Map No. 2015-
01 to allow subdivision of one existing parcel into 35 individual lots for
single - family residences, and 10 lettered lots for common areas and
private streets for the property located at 520 South Harbor Boulevard.
B. Santa Ana Municipal Code Section 34 -127 requires Planning Commission
approval of a tentative tract map for subdivisions.
C. On June 22, 2015, the Planning Commission held a duly noticed public
hearing on Vesting Tentative Tract Map No. 2015 -01.
D. In order to adopt a Vesting Tentative Tract Map, California Government
Code Section 66474 requires the following findings:
1. The proposed project, as conditioned, and its design and
improvements are consistent with the Industrial land use
designation of the General Plan and are otherwise consistent with
all other elements of the General Plan and any applicable specific
plans.
The proposed subdivision, Vesting Tentative Tract Map No.
2015 -01, is consistent with the Urban Neighborhood land
use designation and density prescribed and all other
elements of the General Plan. Specifically, the proposed
subdivision is consistent with several policies within the Land
Use Element of the General Plan, including: Policy 1.5
(Maintain and foster a variety of residential land uses in the
City); Policy 1.7 (Support open space in underserved areas);
and Policy 3.1 (Support development which provides a
positive contribution to neighborhood character and identity).
Resolution No. 2015 -21
Page 1 of 6
2. The proposed project, as conditioned, conforms to all applicable
requirements of the zoning and subdivision codes as well as other
applicable City ordinances.
The proposed subdivision conforms to the minimum
requirements, as well as meets the letter and intent of the
State of California Subdivision Map Act provisions. Vesting
Tentative Tract Map No. 2015 -01 is in keeping with the site
plan review for the project as well as Chapters 34 and 41 of
the Santa Ana Municipal Code. Covenants, Conditions and
Restrictions (CC &Rs) are required for the project, which
need to be approved by the City prior to the recordation of
the final map.
3. The project site is physically suitable for the type and density of the
proposed project.
There are no physical constraints on the site that preclude
development of the site. The proposed site consists of
approximately 2.27 acres of land within the Harbor Mixed
Use Transit Corridor Specific Plan (SP -2), which is physically
suitable for the residential development as proposed.
Access to the site will occur from a single point on Harbor
Boulevard.
4. The design and improvements of the proposed project will not
cause substantial environmental damage or substantially and
avoidably injure fish or wildlife or their habitat.
A proposed subdivision will not cause any substantial
environmental damage or substantially and avoidably injure
fish and wildlife or their habitat. A program -level
Environmental Impact Report (EIR) was prepared pursuant
to the California Environment Quality Act for the new Harbor
Mixed Use Transit Corridor Specific Plan that anticipated up
to 2,000 residential units being built in the Specific Plan
area. The project site is located in an urbanized area, and
there are no known fish or wildlife populations existing on the
project site.
5. The design or improvements of the proposed project will not cause
serious public health problems.
The proposed subdivision will not have any detrimental
effects upon the general public. The short -term and long-
term unavoidable adverse impacts identified in
Environmental Impact Report No. 2014 -01 were addressed
Resolution No. 2015 -21
Page 2 of 6
by the adoption of a Statement of Overriding Considerations
by the City Council. Any other negative or adverse impacts
will be mitigated through mitigation measures identified in
Environmental Impact Report No. 2014 -01 and conditions of
approval for the vesting map.
6. The design or improvements of the proposed project will not conflict
with easements necessary for public access through or use of the
property within the proposed project.
The design or improvements of the proposed project will not
conflict with easements necessary for public access through
or use of the property within the proposed project since there
is no public access easement located within this property.
E. In accordance with the California Environmental Quality Act (CEQA), the
recommended action has been determined to be adequately evaluated in
the previously certified EIR No. 2014 -01 as per Sections 15162 and 15168
of the CEQA guidelines. All mitigation measures in EIR No. 2014 -01 and
associated Mitigation Monitoring and Reporting Program (MMRP) have
been enforced and continue to apply to the proposed project. As required
by the MMPR, a traffic impact analysis was performed to analyze any
potential changes in area traffic as a result of the proposed development.
The study concluded that no additional significant impacts that would
trigger the requirement for additional environmental review.
F. The applicant agrees to indemnify, hold harmless, and defend the City of
Santa Ana, its officials, officers, agents, and employees, from any and all
liability, claims, actions or proceedings that may be brought arising out of
its approval of this project, and any approvals associated with the project,
including, without limitation, any environmental review or approval, except
to the extent caused by the negligence of the City of Santa Ana.
Section 2. The Planning Commission of the City of Santa Ana after conducting
the public hearing hereby approves Vesting Tentative Tract Map No. 2015 -01 as
conditioned in Exhibit A, attached hereto and incorporated as though fully set forth
herein. This decision is based upon the evidence submitted at the abovesaid hearing,
which includes but is not limited to: the Request for Planning Commission Action dated
June 22, 2015 and exhibits attached thereto; and the public testimony, all of which are
incorporated herein by this reference.
Resolution No. 2015 -21
Page 3 of 6
ADOPTED this 22nd day of June 2015 by the following vote:
AYES:
Commissioners:
Alderete, Bacerra, Bauer, Gartner, Nalle, Verino (6)
NOES:
Commissioners:
None (0)
ABSENT:
Commissioners:
Mill (1)
ABSTENTIONS:
Commissioners:
None (0)
J es Gartner
Chairman
APPROVED AS TO FORM:
Sonia R. Carvalho, City Attorney
Lisa Storck
Assistant City Attorney
owl
CERTIFICATE OF ATTESTATION AND ORIGINALITY
I, KAREN GERARDO, Planning Commission Secretary, do hereby attest to and certify
the attached Resolution No. 2015 -21 to be the original resolution adopted by the
Planning Commission of the City of Santa Ana on June 22, 2015.
Date:
Planning Commission Secretary
City of Santa Ana
Resolution No. 2015 -21
Page 4 of 6
EXHIBIT A
Conditions of Approval for Vesting Tentative Tract Map No. 2015 -01
Vesting Tentative Tract Map No. 2015 -01 is approved subject to compliance, to the reasonable
satisfaction of the Planning Manager, with all applicable sections of the Santa Ana Municipal Code,
the California Administrative Code, the California Building Standards Code and all other applicable
regulations.
The applicant must comply in full with each and every condition listed below prior to exercising the
rights conferred by this vesting tentative tract map.
The applicant must remain in compliance with all conditions listed below throughout the life of the
vesting tentative tract map. Failure to comply with each and every condition may result in the
revocation of the vesting tentative tract map.
A. Planning Division
1. The project shall comply with all conditions, standards, requirements, plans, and elevations
approved by the Development Review Committee (DRC) for the development project (DP No.
2014 -23).
2. Covenants, Conditions and Restrictions (CC &Rs) for this project must be reviewed and
approved by City prior to approval of the final tract map. At a minimum, the CC &Rs shall
include provisions pertaining to owner occupancy, restrictions on home -based businesses,
the prohibition of storage on balconies, means for securing any publicly - accessible open
spaces, and a restriction on truck delivery hours to non -peak periods.
3. The final landscape plan shall depict installation of a perimeter block wall on the project site
except in front yard setback areas. The landscape plan shall also contain perimeter block wall
construction details, finishes, decorative elements, and accommodation for landscaping to
deter graffiti.
4. All real estate signage must be removed from the site within one year from the date of
installation. An extension of time may be granted as determined by the Planning Manager.
5. All site activities associated with grading and construction shall be screened by temporary
construction fencing. Such fencing shall be secured and contain durable green mesh.
6. Graffiti on any portion of the project site before, during, and after construction shall be removed
within 24 hours of first appearance.
7. Should the project be built in phases, any phase shall at all times comply with the standards of
the Harbor Mixed Use Transit Corridor Specific Plan.
Resolution No. 2015 -21
Page 5 of 6
8. The final map must be approved and recorded prior to the sale of the first unit.
9. The final map and all improvements required to be made or installed by the
subdivider must be in accordance with the design standards and specifications of
the Santa Ana Municipal Code and the requirements of the State Subdivision
Map Act.
10. Development within the area of the map is subject to development and permit
fees in effect at the time of permit issuance.
11. Development within the area of the map is subject to design and development
standards in effect at the time of permit issuance.
12. Two copies of the recorded final map and CC &Rs shall be submitted each to the
Planning Division, Fire Department, Building Division, and Public Works Agency
within 10 days of recordation.
13. Pursuant to Section 66474.9(b) of the Subdivision Map Act, the applicant shall
defend, indemnify, and hold harmless the City, and its agents, officers, and
employees from any claim, action, or proceeding against the City or its agents,
officers, or employees to attack, set aside, void, or annul, any approval of the
City concerning this subdivision application, which action is brought within the
time period provided for in Section 66499.37.
B. Police Department
1. Building and unit addressing must comply with the City's emergency service
standards.
2. Prior to submittal into Building plan check, the applicant shall provide a
photometric study to the Police Department showing compliance with the 1
footcandle requirement for the project site.
Resolution No. 2015 -21
Page 6 of 6