HomeMy WebLinkAbout23A - PROJ - CONCRETE IMPROVEMENTSREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
SEPTEMBER 1, 2015
TITLE:
AWARD CONTRACT FOR CITYWIDE
CONCRETE IMPROVEMENTS
(PROJECT 166849)
(STRATEGIC PLAN NOS. 6, 1B, 1C & 1G)
CITY MANAGER
RECOMMENDED ACTIONS
CLERK OF COUNCIL USE ONLY:
APPROVED
❑ As Recommended
❑ As Amended
❑ Ordinance on tat Reading
❑ Ordinance on 2ntl Reading
❑ Implementing Resolution
❑ Set Public Hearing For
CONTINUED TO
FILE NUMBER
1. Reject the sole bid received on July 8, 2015, from Excel Paving Company (EPC) in the
amount of $900,000 for the construction of the Citywide Concrete Improvements.
2. Authorize the City Manager and the Clerk of the Council to execute a construction contract to
Ruiz Concrete & Paving Inc., the lowest responsible bidder, in accordance with the Base Bid,
totaling $607,095, for the construction of the Citywide Concrete Improvements, subject to
nonsubstantive changes approved by the City Manager and the City Attorney.
3. Approve the Project Cost Analysis for a total estimated project delivery cost of $789,155
DISCUSSION
Awarding a construction contract to Ruiz Concrete & Paving, Inc., will allow the City to proceed
with the Citywide Concrete improvements which are part of the Fiscal Year 2014 -15 Capital
Improvement Program. This project includes replacement of damaged concrete sidewalks,
curbs, gutters, wheelchair ramps, driveway approaches, and concrete pavement at high priority
locations (Exhibit 1). The locations were selected from a list of community requests that have
been field verified and ranked in terms of safety need. The project design is complete and bid
procedures have been followed as established by the City's Municipal Code and in accordance
with the Pubic Contracts Code.
The original project was advertised for bids on June 16 and 17, 2015. On July 8, 2015, the City
received and opened only one bid for this project. Staff speculates that only one bid was
received because "Non- Motorized Connectivity" was included as part of the job title. Staff
recommends rejecting that bid because it was nearly 50 percent higher than the engineer's
estimate.
23A -1
Contract Award for Citywide Concrete Improvements
September 1, 2015
Page 2
Staff re- advertised the project on July 17 and 18, 2015, and expanded the outreach to improve
bid advertisement and participation by contractors in the bid process. The re- advertised project
yielded seven bids which were opened on August 3, 2015. The following is a summary of the
results:
Contractor Participation Data
Santa Ana contractors receiving notices
1
Contractors requesting bidding documents
7
Bids received
7
Bids received from Santa Ana contractors
1
Bid Results Summary
RANK
BIDDER'S NAME
LOCATION
BID
1
Ruiz Concrete & Paving, Inc.
Long Beach
$607,094.33
2
All American Asphalt
Corona
$691,276.00
3
Elite Bobcat Service
Corona
$708,235.00
4
Hardy & Harper, Inc.
Santa Ana
$733,000.00
5
Excel Paving Company
Long Beach
$794,868.00
6
Vido Samarzich, Inc.
Alta Loma
$861,834.00
7
Nobest, Inc.
Westminster
$908,662.00
All seven bids were deemed responsive. Ruiz Concrete & Paving, Inc. submitted the lowest
responsive bid in the amount of $607,095, which compares favorably with the engineer's estimate
of $630,000. Therefore, staff recommends award of this contract to Ruiz Concrete & Paving, Inc.
Not all sidewalk repairs Citywide will be completed under this contract. Staff has started a study
to evaluate all of the sidewalks and pedestrian pathways in the City. That study will result in a
comprehensive priority list based on many more factors. Staff will follow up with another
construction project to repair concrete sidewalks based on the updated list. The study and its
corresponding priority list will be available for review at the end of 2015.
STRATEGIC PLAN ALIGNMENT
Approval of this item supports the City's efforts to meet Goal #6 Community Facilities &
Infrastructure, Objective #1 (establish and maintain a Community Investment Plan for all City
assets), Strategy B (equitably maintain existing streets and associated assets in a state of good
repair so they are clean, safe, and aesthetically pleasing for all users), Strategy C (invest
23A -2
Contract Award for Citywide Concrete Improvements
September 1, 2015
Page 3
resources and technology to extend the service life of existing infrastructure to protect the City's
investment and support a high quality of life standard), and Strategy G (develop and implement
the City's Capital Improvement Program in coordination with the Community Investment Plan -
e.g., neighborhood streets, traffic improvements, etc.).
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the recommended actions are
exempt from further review. Categorical Exemption Environmental Review No. 2015 -67, was
filed for this project. In addition, a Certification of Categorical Exclusion and Statutory Worksheet
have been prepared in accordance with the National Environmental Policy Act.
FISCAL IMPACT
The Project Cost Analysis has estimated project expenditures to be $789,155, which includes the
construction contract, construction administration, survey and inspection, as well as
contingencies (Exhibit 2). Funds are budgeted in the Liability and Property Insurance Fund
(Account No. 08009051- 62300, Project No. 166849) and will be expended in Fiscal Year 2015-
16.
APPROVED AS TO FUNDS AND ACCOUNTS:
lavipc Francisco Gutierrez
Executive Director
rks Agency Finance & Management Services Agency
FM /EWG /ET
Exhibits: 1. Location Map
2. Cost Analysis
3. Construction Contract
23A -3
23A -4
EXHIBIT 1
SANTA ANA
MPWA
CITY cc CONTRACT AWARD FOR
S T� e R A s CIT MIRE CONCRETE IMPROVEMENTS (16-6849)
t
23A -5
PAGE IOF1
23A -6
COST ANALYSIS
PROJECT NO.16 -6849:
CITYWIDE CONCRETE IMPROVEMENTS
Construction Contract
$607,095.00
Contract Administration
$30,355.00
Inspection and Testing
$42,427.00
Surveying
$18,214.00
Contingencies
$91,064.00
TOTAL ESTIMATED CONSTRUCTION COSTS
$789,155.00
Exhibit 2
23A -7
23A -8
CITE OF SANTA ANA
CONSTRUCTION CONTRACT
PROJECT NO. 16 -6649 CITYWIDE CONCRETE IMPROVEMENTS
'Ibis CONSTRUCTION CONTRACT is made and entered into this ?3 day of September, by and
between the CITY OF SANTA ANA, CALL' OT NIA, a charter city and municipal corporation
organized and existing under the Constitution and laws of the State of California, hereinafter
referred to as "CI'T'Y" mid Ruiz Concrete & Paving, Inc., hereinafter referred to as
"CONTRACTOR ".
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as
follows:
f. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost
and expense necessary to construct and complete in a good and workmanlike manner and to
the satisfaction of the CITY, the following projects, herein after referred to as the
"1PROJEC7"
PROTECT NO, 16.6849 CITY ME CONCRETE IN MOVEMENTS
All work sball be completed in accordance with the Contract Documents prepared by the City's
Public Works Agency,
1 The complete Construction Qmtraet consists of the "Contract Documents," as defined by the
Standard Specifications for Public Works Constnttion and which include the following;
a NoticeInvitiugi3ide
M J; &miation to Bidders
A laid Propossl
u 'Bid Bond
n ContmotForm
e CoattraotBonds
+ specifiozOons
o C,eneral Provisions
Special Provisions
+ 'PtgjectFlaw
Appendices
Contraot Agreement
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for:Publie Works Construction, 2012 edition,
3, CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the
PROJECT the sum total amount not to exceed $602,822.09 as set forth and identified in the
BID PROPOSAL, which is attached hereto and incorporated herein its Exhibit "A" The -3113
Page 1 of 3
23A -9
CITY OF SANTA ANA
CONSTRUCTION CONTRACT
PROJECT NO. 16 -6849 CITYWIDE CONCRETE IWROVElv1ENTS
PROPOSAL contains a schedule of trait price(s) or lump sum(s) based on approximate
quantities only, and the City does not expressly or by implication agree that the actual
amount of work will correspond therewith, but reserves the right to increase ov decrease the
amount of any class or portion of the work or to omit portions of the work as may be deemed
necessary or advisable.
4, CONTRACTOR agrees to complete the PROJECT within the time specified in the Time for
Completion of Improvements section of the HID PROPOSAL (FAibit "A ") including
commencing aonstructioln within the timeframe therein specified aOer issuance of a Notice to
Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on
the PROJECT q salary or wage at least equal to the prevailing salary or wage established for
such work as set forth in the wage detennainations for this work in, accordance with applicable
State and Federal law.
6. CONTRACTOR shall, after award of this Contract, famish two bonds to be approved by the
CITY, one in the amount of One hundred Percent (100 %) of the Contract price, to guarantee
The faithful performance of the work (Performat oe Bond), and one in the amount of One
Hundred Percent (100 1/4) of the Contract price to guarantee payment of all claims for labor
and materials furnished (Payment Bond). This Contract shall not become effective until such
bonds are supplied to and approved by the CITY. CONTRACTOR shalt, prior to the release
of the performance and payment bonds or the retention payment, furnish a warranty
performance and payment bond equal to at least ten (10 %) percent of the final Contract price
or $1,000, whichever is greater (Warranty Bond).
7. CONTRACTOR shall, upon project completion as a condition of project acceptance, fi.u7aish
a. Warranty Payment and performance bond to be approved by the CITY, in the amount of
Twenty -hive Percent (25 %) of the Contract price, to warrant the work done under said
Contract Agreement against material or quality defects for a period of one year after
acceptance by the AGENCY,
s. CONTRACTOR shall„ after award of this Contract, furnish Certificates of Liability
Insurance and Worker's Compensation Insurance as outlined in the Gonoral Provisions, to be
approved by the CM— a
Page 2 of d
23A -10
CITY OF SANTA ANA
CONSTRUCTION CONTRACT
PROJECT NO. 16 -6849 CITYWIDE CONCRETE IMPROVEMENTS
IN WrrNESS WHEREOF, the parties hereto have executed this Construction Contract on the
day and year first above written,
ATTEST:
MARIA D. HUIZAR
Clerk of the Council
APPROVED AS TO FORM:
SONIA R. CARVALIIO
City Attomcy
By
j ' se andoval
,f Assistant City ey -
CITY OF SANTA, ANA
DAVID CAVAZOS
City Manager
RECOMMENDED FOR APPROVAL;
Fred Mousavipour, P.E.
Executive Director, Public Works Agency
CONTRACTOR:
Ruiz Concrete & Paving, c.
Ey.
Title: t
Page 3 of 3
23A -11
23A -12