HomeMy WebLinkAbout23B - PROJ - BIKE LANESREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
SEPTEMBER 1, 2015
TITLE:
AWARD CONTRACT TO CHRISP
COMPANY FOR INSTALLATION OF
CLASS II BIKE LANES ON NEWHOPE,
CIVIC CENTER DRIVE, AND GRAND
(PROJECT 166851)
(STRATEGIC PLAN NO. 6, 1B & 1G)
CITY MANAGER
RECOMMENDED ACTION
CLERK OF COUNCIL USE ONLY:
APPROVED
❑ As Recommended
❑ As Amended
❑ Ordinance on 1" Reading
❑ Ordinance on 2nd Reading
❑ Implementing Resolution
❑ Set Public Hearing For_
CONTINUED TO
FILE NUMBER
1. Authorize the City Manager and the Clerk of the Council to execute a construction contract to
Chrisp Company, the lowest responsible bidder, in accordance with the unit bid prices,
totaling $166,741.60, for construction of the Newhope, Civic Center, and Grand Bike Lanes,
subject to nonsubstantive changes approved by the City Manager and the City Attorney.
2. Approve the Cost Analysis for a total estimated project delivery cost of $222,715.42.
DISCUSSION
Approval of the recommended action will result in the installation of Class II (on- street) bike lanes
on Newhope Street from First Street to McFadden Avenue, Civic Center Drive from Bristol Street
to Broadway, and Grand Avenue from Twenty -first Street to Fairhaven Avenue (Exhibit 1). The
proposed bike lanes are consistent with the City's Bicycle Master Plan and will extend and
connect to existing and planned bike paths. Once completed, these bike lanes will improve
mobility and safety of bicyclists, while also accommodating traffic flow.
A Notice Inviting Bids was advertised on July 11 and July 13, 2015, and bids were opened on
August 3, 2015. The following is a summary of the bid invitations mailed and received, and the
bid results:
Contractor Participation Data
Santa Ana contractors requesting bid documents
0
Contractors requesting bid documents
16
Bids received from Santa Ana contractors
0
Bids received
3
2313-1
Award Contract to Chrisp Company for
Installation of Class II Bike Lanes
September 1, 2015
Page 2
Bid Results Summary
RANK
BIDDERS NAME
LOCATION
BID
1
Chrisp Company
Fremont
$166,741.60
2
Orange County Striping Service Inc.
Orange
$173,371.88
3
BC Rentals, Inc. DBA BC Traffic Specialist
Orange
$184,553.00
Three bids were received and deemed responsive, with Chrisp Company submitting the lowest
responsive bid. Their bid in the amount of $166,741.60 is 22 percent lower than the Engineer's
Estimate of $215,000. This contractor has performed similar work for other agencies, therefore
staff recommends awarding a construction contract in the amount bid (Exhibit 2).
STRATEGIC PLAN ALIGNMENT
Approval of this item supports the City's efforts to meet Goal #6 Community Facilities &
Infrastructure, Objective #1 (establish and maintain a Community Investment Plan for all City
assets), Strategy B (equitably maintain existing streets and associated assets in a state of good
repair so they are clean, safe, and aesthetically pleasing for all users), and Strategy G (develop
and implement the City's Capital Improvement Program in coordination with the Community
Investment Plan (e.g., neighborhood streets, traffic improvements, park facilities, bike master
plan, etc.).
ENVIRONMENTAL IMPACT
In accordance with the California Environmental Quality Act, the recommended actions are
exempt from further review. Categorical Exemption Environmental Review No. 2014 -113 was
filed for this project.
FISCAL IMPACT
The estimated total delivery cost of this project is $222,715.42, which includes construction
administration, inspection, testing, survey and contingencies (Exhibit 3). Funds are budgeted in
the Active Transportation Program Fund (Account No. 14817613- 66220, Project 166851) for
expenditure in Fiscal Year 2015 -16.
Executive Director
Public Works Agency
FM /EWG /KW
Exhibits: 1. Location Map
2. Construction Contract
3. Cost Analysis
APPROVED AS TO FUNDS AND ACCOUNTS:
Francisco Gutierrez
Executive Director
Finance & Management Services Agency
23B -2
SANTA ANA City Council Project Nos. 16 -6851 — Newhope, Civic Center and
P.^ Agenda Date Grand Bike Lanes
,a,�oaKSaE „/, September 1.2015
218-13
BUFFER
BUFFER
BIKE LAP
BUFFER
Newhove Street
7
( xhlbit I
23B -4
CITY OF SANTA ANA
Construction Contract
PROJECT NO, 16.6851
NEWHOPE, CIVIC CENTER AND GRAND BIKE LANES
This CONSTRUCTION CONTRACT is made and entered into this 2nd day of September,
2015, by and between the CITY OF SANTA ANA, CALIFORNIA, a charter city and municipal
corporation organized and existing wider the Constitution and laws of the State of Califortxia,
hereinafter referred to as "CITY" and CHRISP COMPANY, hereinafter referred to as
"CONTRACTOR",
The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as
follows;
1. CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost
and expense necessary to construct and complete In a good and workmanlike manner and to
the satisfaction of the City Engineer of the CITY, the Newbope, Civic Center and Grand
Bike Lanes, hereinafter referred to as the "Work of Improvement ", identified in and in
accordance with the Contract Documents prepared by the City's Public Works Agency and
approved by the City Council,
2. The complete Construction Contract consists of the "Contract Documents," as defined by the
Standard Specifications for Public Works Construction and which include the following;
• Notice Inviting Bids
• Information to Bidders
• Bid Proposal
• Bid Bond
• Contract Form
• Contract Bonds
• General Provisions
• Special Provisions
• Proj cot Plans
• Appendices
In case of conflict between the Contract Documents, the precedence of documents shall be as
established in the Standard Specifications for Public Works Construction.
3. CITY agrees to pay and CONTRACTOR agrees to accept in full payment to complete the
Work of Improvement the surn total amount not to cxoeed $166,741.60, as set forth and
identified in the BID PROPOSAL, which is attached hereto and incorporated herein as
Exhibit "A ". The BID PROPOSAL contains a schedule of unit prico(s) or lump sum(s)
based on approximate quantities only, and the City does not expressly or by implication
agree that the actual amount of work will correspond therewith, but reserves the right to
Page 1 of 3
Exhibit 2
23B -5
CITY OF SANTA ANA
Construction Contract
PROJECT NO, 16 -6851
NEWHOPE, CIVIC CENTER AND GRAND BIKE LANES
increase or decrease the amount of any class or portion of the work or to omit portions of tine
work as may be deemed necessary or advisable.
4, CONTRACTOR. agrees to complete the Work of IrnprDvement within the tone specified in
the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A ")
including commencing construction within the timeframe therein specified after issuance of a
Notice to Proceed.
5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on
the Work of Improvement a salary or wage at least equal to the prevailing salary or wage
established for such work as set forth in the wage determinations for this work in accordance
with applicable State and Federal law.
6. CONTRACTOR shall., after award of this Contract, Atmish two bonds to be approved by the
CITY, one in the amount of One Hundred Percent (100 %) of the Contract price, to guarantee
the faithful performance of the work (Performance Bond), and one in the amount of One
Hundred Percent (100 1/6) of the Contract price to guarantee payment of ail claims for labor
and materials furnished (Payment Bond). This Contract shall not become effective until such
bonds are supplied to and approved by the CITY. CONTRACTOR shall, prior to the release
of the performance and payment bonds or the retention payment, furnish a warranty
performance and payment bond equal to at least ten (10 %) percent of the final Contract price
or $1,000, whichever is greater ("Warranty Bond).
7, CONTRACTOR shall, upon project completion as a condition of project acceptance, furnish
a Warranty Payment and Performance bond to be approved by the CITY, in the amount of
Twenty -Five Percent (25 %) of the Contract price, to warrant the work done under said
Contraot Agreement against material or quality defects for a period of one year after
acceptance by the AGENCY,
CONTRACTOR shall, after award of this Contract, farnish Certificates of Liability
Insurance and Worker's Compensation Insurance as outlined in the General Provisions, to be
approved by the CITY. #
Page 2 of 3
PWEW
CITY OF SANTA ANA
Construction Contract
PROJECT NO, 16 -6551
NEWI-IOPE, CIVIC CENTER AND GRAND BIKE LANES
IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the
day and year first above written,
ATTEST:
MARIA D. HUIZAR
Clerk of the Council
APPROVED AS TO FORM:
SONIA R. CARVALI -10
Citinef y
BY
doval
°-
sistant City Attorney
CITY OF SANTA ANA
DAVID CAVAZOS
City Manager
RECOMiYIENDED FOR APPROVAL;
Fred Mousavipour, P,E.
Executive Director, Public Works Agency
CONTRACTOR:
Chrisp Company
By:
Title:
Page 3 of 3
23B -7
r
COST ANALYSIS
PROJECT 166851; BIKE LANES ON NEWHOPE STREET, CIVIC
CENTER DRIVE AND GRAND AVENUE
Construction Contract $166,741.60
Contract Administration $6,590
. ...............................
Inspection and Testing $16,036
Contingencies $33,348
TOTAL ESTIMATED CONSTRUCTION COSTS
Exhibit 3
23B -9
$222,715
23B -10