RESOLUTION NO. 2017-21
A RESOLUTION OF THE PLANNING COMMISSION OF THE
CITY OF SANTA ANA APPROVING CONDITIONAL USE PERMIT
NO. 2017-15 AS CONDITIONED TO ALLOW A 60 -FOOT TALL
WIRELESS FACILITY LOCATED AT 2802 SOUTH FLOWER
STREET
BE IT RESOLVED BY THE PLANNING COMMISSION OF THE CITY OF SANTA ANA
AS FOLLOWS:
Section 1. The Planning Commission of the City of Santa Ana hereby finds,
determines and declares as follows:
A. American Tower Corp. (Applicant) is requesting approval of Conditional Use
Permit No. 2017-15 to renew the entitlements of an existing 60 -foot high major
wireless communications facility disguised as a palm tree (mono -palm) located at
2802 South Flower Street.
B. Pursuant to Santa Ana Municipal Code (SAMC) Section 41-198.10, a Conditional
Use Permit (CUP) is required for major wireless communications facilities
established in the City of Santa Ana.
C. SAMC Section 41-198.13 states that major wireless communications facilities
shall be approved for a period not to exceed five (5) years, although subsequent
State legislative acts have required that such facilities be approved for a period of
not less than ten (10) years.
D. As the current facility has reached the end of its 10 year mark, the Applicant is
required to apply for a CUP to renew the entitlements in order to maintain the
current facility.
E. In June 28, 1999, the Planning Commission held a duly noticed public hearing on
Conditional Use Permit No. 1999-10 to approve a new 60 -foot mono -pine
wireless facility. The application was approved at a 6-0 vote (Commissioner
Verino absent).
F. On May 22, 2017, the Planning Commission held a duly noticed public hearing
on Conditional Use Permit No. 2017-15.
Section 2. The Planning Commission determines that the following findings, which
must be established in order to grant this Conditional Use Permit pursuant to SAMC Section
41-638, have been established for Conditional Use Permit No. 2017-15 to allow a 60 -foot tall
wireless facility:
1. That the proposed use will provide a service or facility which will contribute
to the general well-being of the neighborhood or the community.
Resolution No. 2017-21
Page 1 of 5
The project will continue to provide a service which will contribute to
the community. The major wireless communication facility will
continue to provide a service to Santa Ana residents, businesses
and motorists who subscribe to American Tower Corp. services by
providing cellular service and data coverage for its users in the
center city sector of Santa Ana.
2. That the proposed use under the circumstances of the particular case will
not be detrimental to the health, safety, or general welfare of persons
residing or working in the vicinity.
The issuance of a new conditional use permit for the facility at this
location will not be detrimental to persons residing or working in the
area as the proposed facility will remain in compliance with Federal
law that governs health-related issues for wireless facilities, including
safety regulations from the Federal Communications Commission
(FCC) and Federal Aviation Administration (FAA).
3. That the proposed use will not adversely affect the present economic
stability or future economic development of properties surrounding the
area.
The facility, in conjunction with the onsite improvements, will be
compatible with the surrounding area and will not adversely affect
the economic viability in the area. The stealthing provided by the
facility's location at the rear of the site will not contribute to any
potential visual blight. Moreover, the facility will maintain and
increase the economic stability for this commercial and industrial
area by providing an additional service for business owners, workers,
and residents in the area.
4. That the proposed use shall comply with the regulations and conditions
specified in Chapter 41 for such use.
The use will continue to comply with all provisions pertaining to the
continuation of existing wireless facilities identified in Chapter 41
(Zoning Code) of the Santa Ana Municipal Code. The facility is
stealthed by its design and surrounding landscape and complies with
other standards outlined in the SAMC. Additional improvements to
the tower will screen the tower and antennas, bringing the facility
into closer compliance with SAMC standards.
5. That the proposed use will not adversely affect the General Plan or any
specific plan of the City.
The major wireless communication facility will not adversely affect
the General Plan as cellular facilities that are designed to be
compatible with the surrounding environment are consistent with the
goals and objectives of the Land Use Element. Goal 1 promotes a
balance of land uses to address community needs, which includes
means of communication that will be served by the facility. In
addition, Goals 3 and 5 require preservation of neighborhood
character and integrity as well as mitigation of developments'
impacts. The mono -palm's location minimizes visual impact on the
area and assists with the stealthing of the equipment. Further,
Resolution No. 2017-21
Page 2 of 5
Policy 2.2 encourages land uses that accommodate the City's
needs for services. Enhancing a cell phone provider's coverage in
the area adds to the services that are readily available for business
owners, workers, and residents in the immediate vicinity.
G. In accordance with the California Environmental Quality Act (CEQA) the
recommended action is exempt from CEQA per Section 15061(b)(3). This
exemption applies to projects where it can be seen with certainty that there is no
possibility that the activity in question may have a significant effect on the
environment. The project proposes to renew an existing major wireless facility
through the issuance of a new CUP. No expansion of square footage or physical
land disturbances are proposed as part of the project. Categorical Exemption
Environmental Review No. 2016-53 will be filed for this project.
Section 3. The Applicant agrees to indemnify, hold harmless, and defend the City of
Santa Ana, its officials, officers, agents, and employees, from any and all liability, claims,
actions or proceedings that may be brought arising out of its approval of this project, and any
approvals associated with the project, including, without limitation, any environmental review or
approval, except to the extent caused by the sole negligence of the City of Santa Ana.
Section 4. The Planning Commission of the City of Santa Ana after conducting the
public hearing hereby approves Conditional Use Permit No. 2017-15, as conditioned in Exhibit
A, attached hereto and incorporated herein. This decision is based upon the evidence
submitted at the abovesaid hearing, which includes, but is not limited to: the Request for
Planning Commission Action dated May 22, 2017, and exhibits attached thereto; and the
public testimony, all of which are incorporated herein by this reference.
ADOPTED this 22nd day of May, 2017 by the following vote:
AYES: Commissioners: ALDERETE, BACERRA, CONTRERAS-LEO,
MCLOUGHLIN, MENDOZA, NGUYEN, VERINO (7)
NOES: Commissioners:
ABSENT: Commissioners:
ABSTENTIONS: Commissioners:
L AW 4d/4-�°
L vette Verino
Chairperson
Resolution No. 2017-21
Page 3 of 5
APPROVED AS TO FORM:
Sonia R. Carvalho, City Attorney
By: �z %L
Lisa Storck
Assistant City Attorney
CERTIFICATE OF ATTESTATION AND ORIGINALITY
I, SARAH BERNAL, Commission Secretary, do hereby attest to and certify the attached
Resolution No. 2017-21 to be the original resolution adopted by the Planning Commission of
the City of Santa Ana on May 22, 2017.
Date:
Recording Secretary
City of Santa Ana
Resolution No. 2017-21
Page 4 of 5
3
EXHIBIT A
Conditions for Approval
Conditional Use Permit No. 2017-15 is approved subject to compliance, to the reasonable
satisfaction of the Planning Manager, with all applicable sections of the Santa Ana Municipal
Code, the California Administrative Code, the California Building Standards Code and all other
applicable regulations.
The Applicant must comply in full with each and every condition listed belowrip or to exercising
the rights conferred by this conditional use permit.
The Applicant must remain in compliance with all conditions listed below throughout the life of
the conditional use permit. Failure to comply with each and every condition may result in the
revocation of the conditional use permit.
1. The Applicant must comply with all conditions and requirements of the Development
Review Committee for the development project (DP No. 2016-18).
2. The Applicant shall replace all existing fronds with new stealth palm fronds similar in type
to the Mexican Fan palm to the existing tower within 180 days of the effective date of this
conditional use permit.
3. Any amendment to this conditional use permit must be submitted to the Planning
Division for review. At that time, staff will determine if administrative relief is available or
the conditional use permit must be amended.
4. The facility shall be maintained as per approved plans. Any damage to existing
structures, walls, parking areas, or landscaping must be repaired.
5. The permit Applicant shall provide a 24-hour phone number to which interference
problems may be reported. This condition will also apply to all existing facilities in the
City of Santa Ana.
6. The permit Applicant will provide a "single point of contact" in its Engineering and
Maintenance Departments to insure continuity on all interference issues. The name,
telephone number, fax number and e-mail address of that person shall be provided to
the City's designated representative upon activation of the facility.
7. The permit Applicant shall ensure that lessee or other user(s) shall comply with the
terms and conditions of this permit, and shall be responsible for the failure of any lessee
or other users under the control of permit Applicant to comply.
Resolution No. 2017-21