| REQUEST FOR 
<br />COUNCIL ACTION 
<br />CITY COUNCIL MEETING DATE: 
<br />SEPTEMBER 5, 2017 
<br />TITLE: 
<br />AWARD CONTRACT TO USS CAL 
<br />BUILDERS, INC., FOR CONSTRUCTION 
<br />OF DOWNTOWN PARKING FACILITY 
<br />IMPROVEMENTS (PROJECT NOS. 
<br />16-1301,16-1302,16-1303 , 16-1304) 
<br />(STRATEGIC PLAN NOS. 6, 1G)/ 
<br />RECOMMENDED ACTION 
<br />CLERK OF COUNCIL USE ONLY: 
<br />APPROVED 
<br />CONTINUED TO 
<br />FILE NUMBER 
<br />1. Reject all bids received on March 30, 2017, for construction of the Downtown Parking Facility 
<br />Improvements project, due to changes in the scope of work. 
<br />2. Award a contract and authorize the City Manager and Clerk of the Council to execute a 
<br />construction contract to USS Cal Builders, Inc., the lowest responsible bidder, in accordance 
<br />with the base bid in the amount of $2,809,485, for the term beginning upon execution of the 
<br />contract and ending upon project completion, for the Downtown Parking Facility 
<br />Improvements project, subject to nonsubstantive changes approved by the City Manager and 
<br />the City Attorney. 
<br />3. Approve the Project Cost Analysis for a total estimated construction delivery cost of 
<br />$3,275,000, which includes the contract bid amount, administration, inspection and testing, 
<br />and an authorized contingency of $345,515. 
<br />DISCUSSION 
<br />As part of the Council approved Downtown Enhancement and Parking Plan, this project will 
<br />improve four downtown parking facilities located at 310 North Birch Street (3rd/Birch Parking 
<br />Structure), 420 North Main Street (5th/Main Parking Structure), 300 East Fifth Street 
<br />(5th/Spurgeon Parking Structure), and 301 North Bush Street (3rd/Bush Parking Lot). (See 
<br />Exhibit 1.) The scope of work for the parking structures includes removal of existing parking 
<br />access control equipment and attendant booths; installation of new parking access control 
<br />equipment, on -foot pay stations, and a parking control management central station; and 
<br />renovation of the existing restrooms at the 5th/Spurgeon Parking Structure. 
<br />The scope of work for the 3rd/Bush Parking Lot includes removal of the existing on -foot pay 
<br />station, installation of new on -foot pay station, and construction of a new wheelchair access ramp 
<br />As Recommended ' S I } 
<br />As Amended 
<br />❑ 
<br />Ordinance on 1s' Reading 
<br />❑ 
<br />Ordinance on 2ntl Reading 
<br />❑ 
<br />Implementing Resolution 
<br />❑ 
<br />Set Public Hearing For 
<br />CONTINUED TO 
<br />FILE NUMBER 
<br />1. Reject all bids received on March 30, 2017, for construction of the Downtown Parking Facility 
<br />Improvements project, due to changes in the scope of work. 
<br />2. Award a contract and authorize the City Manager and Clerk of the Council to execute a 
<br />construction contract to USS Cal Builders, Inc., the lowest responsible bidder, in accordance 
<br />with the base bid in the amount of $2,809,485, for the term beginning upon execution of the 
<br />contract and ending upon project completion, for the Downtown Parking Facility 
<br />Improvements project, subject to nonsubstantive changes approved by the City Manager and 
<br />the City Attorney. 
<br />3. Approve the Project Cost Analysis for a total estimated construction delivery cost of 
<br />$3,275,000, which includes the contract bid amount, administration, inspection and testing, 
<br />and an authorized contingency of $345,515. 
<br />DISCUSSION 
<br />As part of the Council approved Downtown Enhancement and Parking Plan, this project will 
<br />improve four downtown parking facilities located at 310 North Birch Street (3rd/Birch Parking 
<br />Structure), 420 North Main Street (5th/Main Parking Structure), 300 East Fifth Street 
<br />(5th/Spurgeon Parking Structure), and 301 North Bush Street (3rd/Bush Parking Lot). (See 
<br />Exhibit 1.) The scope of work for the parking structures includes removal of existing parking 
<br />access control equipment and attendant booths; installation of new parking access control 
<br />equipment, on -foot pay stations, and a parking control management central station; and 
<br />renovation of the existing restrooms at the 5th/Spurgeon Parking Structure. 
<br />The scope of work for the 3rd/Bush Parking Lot includes removal of the existing on -foot pay 
<br />station, installation of new on -foot pay station, and construction of a new wheelchair access ramp 
<br /> |