Laserfiche WebLink
EXHIBIT 2 <br />Doors/Windows <br />$ 297,000 <br />$ 280,579 <br />$ 41,341.91 <br />$ 390,121 <br />$ 68,200 <br />Change of Scope <br />The following doors were added to the scope: <br />- Wood doors (City decision to upgrade material) <br />- 2 hour glass door <br />- Dining room accordion door <br />- Rollout door <br />- Glass bifold door <br />- City requested to order more doors due to previous order being late <br />Fold -Up Door <br />$ 49,000 <br />$ <br />$ 6,960.53 <br />$ 6,961 <br />$ <br />Change of Scope <br />CMU Block Wall <br />$ 160,000 <br />$ 199,202 <br />$ <br />$ 199,202 <br />$ <br />Change of Scope and increase in material cost <br />- Significant increase in material cost <br />Stucco for CMU Block Wall <br />$ <br />$ 20,000 <br />$ 15,021.24 <br />$ 65,021 <br />$ 30,000 <br />Change of Scope <br />- Preferred method of ICF was rejected by building and safety <br />Shade Structures <br />$ 100,000 <br />$ 40,333 <br />$ 10,618.81 <br />$ 120,952 <br />$ 70,000 <br />Increase in material cost <br />- Steel prices have increased dramatically over the life of the project <br />Shade Sales <br />$ <br />$ 10,000 <br />$ <br />$ 10,000 <br />$ <br />Interior Finishes(Floor/Wall) <br />$ 300,000 <br />$ 65,467 <br />$ 126,191.09 <br />$ 215,258 <br />$ 23,600 <br />Change of Scope <br />Interior Paint <br />$ <br />$ 60,004 <br />$ 45,710.48 <br />$ 105,714 <br />$ <br />Upstairs Carpeting <br />$ <br />$ <br />$ <br />$ 24,230 <br />$ 24,230 <br />Change of Scope <br />- Looking for less expensive substitutes <br />Upstairs Vinyl <br />$ <br />$ <br />$ <br />$ 77,389 <br />$ 77,389 <br />Change of Scope <br />- Looking for less expensive substitutes <br />Grind and Seal <br />$ <br />$ <br />$ 73,074 <br />$ 73,074 <br />$ <br />Change of Scope <br />Epoxy Kitchen <br />$ <br />$ <br />$ 21,555 <br />$ 21,555 <br />$ <br />Change of Scope <br />Exterior Finishes/Landscaping <br />$ 25,000 <br />$ 27,031 <br />$ <br />$ 27,031 <br />$ <br />Playground/Fencing <br />$ <br />$ <br />$ 11,470 <br />$ 13,470 <br />$ 2,000 <br />Change of Scope <br />Exterior Fencing <br />$ <br />$ <br />$ <br />$ 4,000 <br />$ 4,000 <br />Change of Scope <br />Plant/Tree Allowance <br />$ <br />$ <br />$ <br />$ 13,000 <br />$ 13,000 <br />Change of Scope <br />Pea Gravel <br />$ <br />$ <br />$ <br />$ 4,000 <br />$ 4,000 <br />Change of Scope <br />Fiber Glass Bender Board <br />$ <br />$ <br />$ <br />$ 600 <br />$ 600 <br />Change of Scope <br />Backyard Turf <br />$ <br />$ <br />$ <br />$ 4,500 <br />1 $ 4,500 <br />Change of Scope <br />Irrigation <br />$ <br />$ <br />$ <br />$ 5,000 <br />$ 5,000 <br />Change of Scope <br />Sod Grass <br />$ <br />$ <br />$ <br />$ 5,000 <br />$ 5,000 <br />Change of Scope <br />Exterior Painting <br />$ 75,000 <br />$ <br />$ <br />$ 64,286 <br />$ 64,286 <br />Change of Scope <br />- Recently added to the scope as there was additional work to repair and complete work not completed by the former contractor <br />Camera/Security System <br />$ 140,000 <br />$ 72,436.85 <br />$ 12,752.73 <br />$ 152,440 <br />$ 67,250 <br />Change of Scope <br />- Not part of original scope (part of FF&E) <br />Lighting Package <br />$ 200,520 <br />$ 221,335.09 <br />$ <br />$ 228,335 <br />$ 7,000 <br />- Needed to substitute lights because of back order and new lights were more expensive <br />Roof Screening <br />$ 76,146 <br />$ <br />$ <br />$ 76,146 <br />$ 76,146 <br />Change of Scope <br />- City permitting process required roof screening <br />Roof Framing Allowance <br />$ 300,000 <br />$ <br />$ 21,225.70 <br />$ 300,000 <br />$ 78,774 <br />Change of Scope <br />Column Replacement <br />$ 25,000 <br />$ <br />$ <br />$ <br />$ <br />Unforeseen Circumstance and Change of Scope <br />Miscellaneous <br />$ 100,000 <br />$ <br />$ <br />$ 100,000 <br />$ 100,000 <br />- Per City, amount determined per discussions with City Staff. <br />COVIDTesting <br />$ <br />$ <br />$ 3,380.00 <br />$ 3,380 <br />$ <br />Site Cleanup <br />$ <br />$ <br />$ 8,000.00 <br />$ 28,000 <br />$ 20,000 <br />Unforeseen Circumstance <br />- PWA mandating cleanup at the site <br />Rolling Gates and operators <br />$ <br />$ <br />$ <br />$ 50,000 <br />$ 50,000 <br />Change of Scope <br />- Planned to use existing gates, but deemed unusable <br />Rec Area Gates and Hardware <br />$ <br />$ <br />$ <br />$ 25,000 <br />$ 15,000 <br />Change of Scope and increase in material cost <br />Subtotal <br />$ 9,643,660 <br />$ 8,639,089 <br />$ 998,724 <br />$ 11,655,203 <br />$ 2,017,391 <br />General Conditions <br />$ 1,055,923 <br />$ 1,066,077 <br />$ <br />$ 1,055,923 <br />$ <br />Extended Timeline <br />- Timeline for project finish date extended due to design and permitting delays; scope of work increased <br />Overhead/Main Office <br />$ 269,077 <br />$ 258,923 <br />$ <br />$ 269,077 <br />$ <br />Extended Timeline <br />- Timeline for project finish date extended due to design and permitting delays; scope of work increased <br />Total <br />$ 10,968,660 <br />$ 9,964,089 <br />$ 998,724 <br />$ 12,980,203 <br />$ 2,017,391 <br />City Council 26 - 43 4/19/2022 <br />