7.7.3 The maximum expected static settlement for the five -story residential structure supported on
<br />a conventional foundation system designed with a maximum bearing pressure of 5,000 psf and
<br />deriving support in the recommended bearing materials is estimated to be less than %2 inch and
<br />occur below the heaviest loaded structural element. Settlement of the foundation system is
<br />expected to occur on initial application of loading. Differential settlement is not expected to
<br />exceed'/a inch over a distance of 20 feet.
<br />7.7.4 It is recommended that either a seismic separation or flexible connection be utilized where the
<br />apartment structures and parking structure may be attached. The design of the connection is at
<br />the discretion of the project structural engineer. Additional settlement analyses should be
<br />performed once the foundation loading configuration for the proposed structures is finalized
<br />to further evaluate the potential for differential settlement between the residential structure and
<br />parking structure. The utilization of a lesser bearing value, or increasing the thickness of
<br />engineered fill below the foundations, would further reduce the anticipated settlements and
<br />could be evaluated once the design becomes more finalized.
<br />7.7.5 It is recommended that flexible utility connections be utilized for all rigid utilities to minimize
<br />or prevent damage to utilities from minor differential movements.
<br />7.7.6 Once the design and foundation loading configurations for the proposed structures proceeds to
<br />a more finalized plan, the estimated settlements presented in this report should be reviewed
<br />and revised, if necessary. If the final foundation loading configurations are greater than the
<br />assumed loading conditions, the potential for settlement should be reevaluated by this office.
<br />7.8 Miscellaneous Foundations
<br />7.8.1 Foundations for small outlying structures, such as block walls up to 6 feet in height, planter
<br />walls or trash enclosures, which will not be structurally supported by the proposed building,
<br />may be supported on conventional foundations deriving support on a minimum of 12 inches
<br />of newly placed engineered fill which extends laterally at least 12 inches beyond the
<br />foundation area. Where excavation and compaction cannot be performed, such as adjacent to
<br />property lines, foundations may derive support in the undisturbed alluvial soils, and should be
<br />deepened as necessary to maintain a minimum 12-inch embedment into the recommended
<br />bearing materials.
<br />Geocon Project No. A9799-88-01
<br />-19-
<br />June 7, 2022
<br />7.8.2 If the soils exposed in the excavation bottom are loose, compaction of the soils will be required
<br />prior to placing steel or concrete. Compaction of the foundation excavation bottom is typically
<br />accomplished with a compaction wheel or mechanical whacker and must be observed and
<br />approved by a Geocon representative. Miscellaneous foundations may be designed for a
<br />bearing value of 1,500 psf, and should be a minimum of 12 inches in width, 18 inches in depth
<br />below the lowest adjacent grade and 12 inches into the recommended bearing material.
<br />The allowable bearing pressure may be increased by up to one-third for transient loads due to
<br />wind or seismic forces.
<br />7.8.3 Foundation excavations should be observed and approved in writing by the Geotechnical
<br />Engineer (a representative of Geocon West, Inc.), prior to the placement of reinforcing steel
<br />and concrete to verify that the excavations and exposed soil conditions are consistent with
<br />those anticipated.
<br />7.9 Lateral Design
<br />7.9.1 Resistance to lateral loading may be provided by friction acting at the base of foundations,
<br />slabs and by passive earth pressure. An allowable coefficient of friction of 0.35 may be used
<br />with the dead load forces in the newly placed engineered fill or undisturbed alluvial soils.
<br />7.9.2 Passive earth pressure for the sides of foundations and slabs poured against newly placed
<br />engineered fill or undisturbed alluvial soils may be computed as an equivalent fluid having a
<br />density of 230 pounds per cubic foot (pcf) with a maximum earth pressure of 2,300 psf. When
<br />combining passive and friction for lateral resistance, the passive component should be reduced
<br />by one-third. A one-third increase in the passive value may be used for wind or seismic loads.
<br />7.10 Concrete Slabs -on -Grade
<br />7.10.1 Concrete slabs -on -grade subject to vehicle loading should be designed in accordance with the
<br />recommendations in the Preliminary Pavement Recommendations section of this report
<br />(Section 7.11).
<br />7.10.2 Subsequent to the recommended grading, concrete slabs -on -grade for structures, not subject
<br />to vehicle loading, should be a minimum of 4 inches thick and minimum slab reinforcement
<br />should consist of No. 3 steel reinforcing bars placed 18 inches on center in both horizontal
<br />directions. Steel reinforcing should be positioned vertically near the slab midpoint.
<br />Geocon Project No. A9799-88-01 -20- June 7, 2022
<br />PHASE 2
<br />STRUCTURAL
<br />FOOTING
<br />TO BE PLACED OVER
<br />/\/\/
<br />>,/A;R 11401
<br />/
<br />INITIAL CONCRETE POUR
<br />_-_-4-_-_-�-_-PHASE 1
<br />STRUCTURAL
<br />CONCRETE
<br />IN jTA/ L p jITj SLOT CUTS
<br />j/
<br />7.6.5 If two-part foundation construction is used, the structural footing will be bounded laterally by
<br />artificial fill and, therefore, passive pressure along the sides of the foundations cannot be
<br />utilized. Resistance to lateral loads should be provided via structural connections to other
<br />portions of the structure.
<br />7.6.6 Continuous footings may be designed for an allowable bearing capacity of 2,500 pounds per
<br />square foot (psf), and should be a minimum of 12 inches in width, 18 inches in depth below
<br />the lowest adjacent grade, and 12 inches into the recommended bearing material.
<br />7.6.7 Isolated spread foundations may be designed for an allowable bearing capacity of 3,000 psf,
<br />and should be a minimum of 24 inches in width, 18 inches in depth below the lowest adjacent
<br />grade, and 12 inches into the recommended bearing material.
<br />7.6.8 The allowable soil bearing pressure above may be increased by 250 psf and 500 psf for each
<br />additional foot of foundation width and depth, respectively, up to a maximum allowable soil
<br />bearing pressure of 5,000 psf.
<br />7.6.9 The allowable bearing pressures may be increased by one-third for transient loads due to wind
<br />or seismic forces.
<br />Geocon Project No. A9799-88-01 - 17 - June 7, 2022
<br />7.6.10 Continuous footings should be reinforced with a minimum of four No. 4 steel reinforcing bars,
<br />two placed near the top of the footing and two near the bottom. The reinforcement for isolated
<br />spread footings should be designed by the project structural engineer.
<br />7.6.11 If depth increases are utilized for the exterior wall footings, this office should be provided a
<br />copy of the final construction plans so that the excavation recommendations presented herein
<br />could be properly reviewed and revised if necessary.
<br />7.6.12 No special subgrade presaturation is required prior to placement of concrete. However, the
<br />slab and foundation subgrade should be sprinkled as necessary; to maintain a moist condition
<br />as would be expected in any concrete placement.
<br />7.6.13 Foundation excavations should be observed and approved in writing by the Geotechnical
<br />Engineer (a representative of Geocon West, Inc.), prior to the placement of reinforcing steel
<br />and concrete to verify that the excavations and exposed soil conditions are consistent with
<br />those anticipated. If unanticipated soil conditions are encountered, foundation modifications
<br />may be required.
<br />7.6.14 This office should be provided a copy of the final construction plans so that the excavation
<br />recommendations presented herein could be properly reviewed and revised if necessary.
<br />7.7 Foundation Settlement
<br />7.7.1 The maximum expected static settlement for the parking structures supported on a
<br />conventional foundation system designed with a maximum bearing pressure of 5,000 psf, and
<br />deriving support in the recommended bearing materials is estimated to be less than
<br />1 inch and occur below the heaviest loaded structural element. Settlement of the foundation
<br />system is expected to occur on initial application of loading. Differential settlement is not
<br />expected to exceed %Z inch over a distance of 20 feet.
<br />7.7.2 The maximum expected static settlement for the seven -story mixed -use structure supported on
<br />a conventional foundation system designed with a maximum bearing pressure of 5,000 psf and
<br />deriving support in the recommended bearing materials is estimated to be less than 1 %2 inches
<br />and occur below the heaviest loaded structural element. Settlement of the foundation system
<br />is expected to occur on initial application of loading. Differential settlement is not expected to
<br />exceed 3/4 inch over a distance of 20 feet.
<br />Geocon Project No. A9799-88-01 _18- June 7, 2022
<br />7.4.9 Foundations for small outlying structures, such as block walls up to 6 feet high, planter walls
<br />or trash enclosures, which will not be tied to the proposed structure, may be supported on
<br />conventional foundations bearing on a minimum of 12 inches of newly placed engineered fill
<br />which extends laterally at least 12 inches beyond the foundation area. Where excavation and
<br />proper compaction cannot be performed, foundations may derive support directly in the
<br />undisturbed alluvial soils, and should be deepened as necessary to maintain a minimum
<br />12-inch embedment into the recommended bearing materials. If the soils exposed in the
<br />excavation bottom are soft or loose, compaction of the soils will be required prior to placing
<br />steel or concrete. Compaction of the foundation excavation bottom is typically accomplished
<br />with a compaction wheel or mechanical whacker and must be observed and approved in
<br />writing by a Geocon representative.
<br />7.4.10 All imported fill shall be observed, tested, and approved by Geocon West, Inc. prior to bringing
<br />soil to the site. Rocks larger than 6 inches in diameter shall not be used in the fill. Import soils
<br />used as structural fill should have an expansion index less than 20 and corrosivity properties
<br />that are equally or less detrimental to that of the existing onsite soils (see Figure 139). Import
<br />soils placed in the building area should be placed uniformly across the building pad or in a
<br />manner that is approved by the Geotechnical Engineer (a representative of Geocon).
<br />7.4.11 Utility trenches should be properly backfilled in accordance with the following requirements.
<br />The pipe should be bedded with clean sands (Sand Equivalent greater than 30) to a depth of at
<br />least I foot over the pipe, and the bedding material must be inspected and approved in writing
<br />by the Geotechnical Engineer (a representative of Geocon). The use of gravel is not acceptable
<br />unless used in conjunction with filter fabric to prevent the gravel from having direct contact
<br />with soil. The remainder of the trench backfill may be derived from onsite soil or approved
<br />import soil, compacted as necessary, until the required compaction is obtained. The use of
<br />minimum 2-sack slurry as backfill is also acceptable. Prior to placing any bedding materials
<br />or pipes, the trench excavation bottom must be observed and approved in writing by the
<br />Geotechnical Engineer (a representative of Geocon).
<br />7.4.12 All trench and foundation excavation bottoms must be observed and approved in writing by
<br />the Geotechnical Engineer (a representative of Geocon), prior to placing bedding sands, fill,
<br />steel, gravel, or concrete.
<br />7.5 Shrinkage
<br />7.5.1 Shrinkage results when a volume of material removed at one density is compacted to a higher
<br />density. A shrinkage factor of between 10 and 20 percent should be anticipated when
<br />excavating and compacting the upper 5 feet of existing earth materials on the site to an average
<br />relative compaction of 92 percent.
<br />Geocon Project No. A9799-88-01
<br />-15-
<br />June 7, 2022
<br />7.4.2 If import soils will be utilized in the building pads, the soils must be placed uniformly and at
<br />equal thickness at the direction of the Geotechnical Engineer (a representative of Geocon
<br />West, Inc.). Soils can be borrowed from non -building pad areas and later replaced with
<br />imported soils.
<br />7.6 Foundation Design
<br />7.6.1 Subsequent to the recommended grading, a conventional shallow spread foundation system
<br />may be utilized for support of the proposed structures provided foundations derive support in
<br />newly placed engineered fill and/or the competent alluvial soils found at and below a depth of
<br />5 feet. It is the intent of the Geotechnical Engineer to allow building foundations to derive
<br />support in both engineered fill and competent alluvial soils for this project if conditions warrant
<br />such an occurrence. All foundation excavations must be observed and approved in writing by
<br />the Geotechnical Engineer (a representative of Geocon) prior to placing steel or concrete. Any
<br />exposed soft soils should be compacted to a dense state or penetrated by proposed foundations
<br />at the direction of the Geotechnical Engineer (a representative of Geocon West, Inc.).
<br />7.6.2 Special excavation measures, such as slot cutting, will be required to construct foundations
<br />along the property line. Recommendations for slot cutting are provided in Section 7.18 of this
<br />report.
<br />7.6.3 Foundations along the property line may be constructed in two phases using slot cutting to
<br />create temporary excavations and quickly restore the majority of the support. It is
<br />recommended that this project be mass graded prior to performing any foundation excavations
<br />along the property lines.
<br />7.6.4 The first phase of foundation construction will be to excavate a temporary slot -cut excavation.
<br />The lower portion of the excavation, once approved by Geocon, can be backfilled with
<br />structural concrete up to the desired bottom of foundation depth. The project structural
<br />engineer should determine if the Phase 1 concrete pour requires any reinforcing and/or a key
<br />between the two pours. The excavation should be backfilled on the same day the excavation is
<br />opened. The second phase of the foundation construction will be to place the reinforced
<br />structural foundation on top of the previously placed Phase 1 concrete. The two-part
<br />foundation construction is illustrated below.
<br />Geocon Project No. A9799-88-01 - 16 - June 7, 2022
<br />7.3.2 Laboratory tests were performed on representative samples of the site materials to measure the
<br />percentage of water-soluble sulfate content. Results from the laboratory water-soluble sulfate
<br />tests are presented in Appendix B (Figure 139) and indicate that the on -site materials possess
<br />sulfate exposure class of "SO" to concrete structures as defined by 2019 CBC Section 1904
<br />and ACI 318-19 Chapter 19.
<br />7.3.3 Geocon West, Inc. does not practice in the field of corrosion engineering and mitigation.
<br />If corrosion sensitive improvements are planned, it is recommended that a corrosion engineer
<br />be retained to evaluate corrosion test results and incorporate the necessary precautions to avoid
<br />premature corrosion of buried metal pipes and concrete structures in direct contact with the
<br />soils.
<br />7.4 Grading
<br />7.4.1 A preconstruction conference should be held at the site prior to the beginning of grading
<br />operations with the owner, contractor, civil engineer and soil engineer in attendance. Special
<br />soil handling requirements can be discussed at that time.
<br />7.4.2 Earthwork should be observed, and compacted fill tested by representatives of Geocon West,
<br />Inc. The existing fill and alluvial soils encountered during exploration are suitable for reuse as
<br />engineered fill, provided any encountered oversize material (greater than 6 inches) and any
<br />encountered deleterious debris is removed.
<br />7.4.3 Grading should commence with the removal of all existing vegetation and existing
<br />improvements from the area to be graded. Deleterious debris such as wood and root structures
<br />should be exported from the site and should not be mixed with the fill soils. Asphalt and
<br />concrete should not be mixed with the fill soils unless approved by the Geotechnical Engineer.
<br />All existing underground improvements planned for removal should be completely excavated
<br />and the resulting depressions properly backfilled in accordance with the procedures described
<br />herein. Once a clean excavation bottom has been established it must be observed and approved
<br />in writing by the Geotechnical Engineer (a representative of Geocon West, Inc.).
<br />Geocon Project No. A9799-88-01
<br />-13-
<br />June 7, 2022
<br />7.4.4 As a minimum, it is recommended that the upper 5 feet of existing earth materials within the
<br />proposed building footprint areas be excavated and properly compacted for foundation and
<br />slab support. Deeper excavations should be conducted as necessary to remove deeper artificial
<br />fill or soft alluvial soil at the direction of the Geotechnical Engineer (a representative of
<br />Geocon). The limits of existing fill and/or soft alluvial soils removal will be verified by the
<br />Geocon representative during site grading activities. The excavation should extend laterally a
<br />minimum distance of 3 feet beyond the building footprint area, including building
<br />appurtenances, or a distance equal to the depth of fill below the foundation, whichever is
<br />greater. Where the recommended lateral over -excavation cannot be performed, such as
<br />adjacent to a property line, foundations should be deepened as necessary to derive support in
<br />the undisturbed alluvial soils found at or below a depth of 5 feet.
<br />7.4.5 All excavations must be observed and approved in writing by the Geotechnical Engineer (a
<br />representative of Geocon). Prior to placing any fill, the upper 12 inches of the excavation
<br />bottom must be scarified, moistened, and proof -rolled with heavy equipment in the presence
<br />of the Geotechnical Engineer (a representative of Geocon West, Inc.). Any exposed soft soils
<br />should be compacted to a dense state or penetrated by proposed foundations at the direction of
<br />the Geotechnical Engineer (a representative of Geocon West, Inc.).
<br />7.4.6 All fill and backfill soils should be placed in horizontal loose layers approximately 6 to
<br />8 inches thick, moisture conditioned to near optimum moisture content, and properly
<br />compacted to a minimum of 90 percent of the maximum dry density per ASTM D 1557 (latest
<br />edition).
<br />7.4.7 It is anticipated that stable excavations for the recommended grading associated with the
<br />proposed structures can be achieved with sloping measures. However, if excavations in close
<br />proximity to an adjacent property line and/or structure are required, special excavation
<br />measures may be necessary in order to maintain lateral support of offsite improvements.
<br />Excavation recommendations are provided in the Temporary Excavations section of this report
<br />(see Section 7.17).
<br />7.4.8. Where new paving is to be placed, it is recommended that all existing fill and soft alluvium be
<br />excavated and properly compacted for paving support. As a minimum, the upper
<br />12 inches of soil should be scarified, moisture conditioned to near optimum moisture content,
<br />and compacted to at least 95 percent relative compaction, as determined by ASTM Test
<br />Method D 1557 (latest edition). Paving recommendations are provided in Preliminary
<br />Pavement Recommendations section of this report (see Sections 7.11 and 7.12).
<br />Geocon Project No. A9799-88-01
<br />-14-
<br />June 7, 2022
<br />Architecture + Planning
<br />17911 Von Karman Ave.
<br />Suite 200
<br />Irvine, CA 92614
<br />ktgy.com
<br />949.851.2133
<br />KTGY Project No: 2017-0934
<br />Project Contact: Debbie Holland
<br />Email: dholland@ktgy.com
<br />Principal: Wil Wong
<br />Project Designer: D. Schoolmeester
<br />Project Director: Debbie Holland
<br />Developer
<br />ED 0 A K
<br />INVESTi1iEN I'S
<br />4199 CAMPUS DRIVE
<br />IRVINE, CA 92612
<br />PHONE NO. (714) 342-2502
<br />Sig
<br />TF
<br />r
<br />N
<br />C)
<br />Q
<br />U
<br />Q
<br />Z
<br />Q
<br />Q
<br />Z
<br />Q
<br />U)
<br />LU
<br />LU
<br />U)
<br />F_
<br />NT
<br />L li
<br />Ln
<br />Ln
<br />06
<br />T_
<br />Nt
<br />m
<br />No. Date Description H
<br />75
<br />00
<br />D
<br />U)
<br />U
<br />w
<br />2
<br />U
<br />Z
<br />Q
<br />J
<br />It is the clients responsibility prior to or during construction to notify the architect in writing
<br />of any perceived errors or omissions in the plans and specifications of which a contractor
<br />thoroughly knowledgeable with the building codes and methods of construction should
<br />reasonably be aware. Written instructions addressing such perceived errors or omissions
<br />shall be received from the architect prior to the client or clients subcontractors proceeding
<br />with the work. The client will be responsible for any defects in construction if these
<br />procedures are not followed.
<br />v,
<br />S�D ARcj,11
<br />ILL
<br />N
<br />No. C29795
<br />0
<br />RENEWAL DATE
<br />AUGUST 31, 2023
<br />qTF OF
<br />0
<br />C��
<br />A
<br />License Stamp
<br />o
<br />GEOTECHNICAL
<br />REPORT
<br />COPYRIGHT (c,
<br />AO-82
<br />
|