7.15.3 If retainingwall drainage is to be provided, the drainage system should be designed in
<br />g p g Y �
<br />accordance with the Retaining Wall Drainage section of this report (see Section 7.14).
<br />7.15.4 It is suggested that the elevator pit walls and slab be waterproofed to prevent excessive
<br />moisture inside of the elevator pit. Waterproofing design and installation is not the
<br />responsibility of the geotechnical engineer.
<br />7.16 Elevator Piston
<br />7.16.1 If a plunger -type elevator piston is installed for this project, a deep drilled excavation will be
<br />required. It is important to verify that the drilled excavation is not situated immediately
<br />adjacent to a foundation, or the drilled excavation could compromise the existing foundation,
<br />especially if the drilling is performed subsequent to the foundation construction.
<br />7.16.2 Casing may be required if caving is experienced in the drilled excavation. The contractor
<br />should be prepared to use casing and should have it readily available at the commencement of
<br />drilling activities. Continuous observation of the drilling and installation of the elevator piston
<br />by the Geotechnical Engineer (a representative of Geocon West, Inc.) is required.
<br />7.16.3 The annular space between the piston casing and drilled excavation wall should be filled with
<br />a minimum of 1 %2-sack slurry pumped from the bottom up. As an alternative, pea gravel may
<br />be utilized. The use of soil to backfill the annular space is not acceptable.
<br />7.17 Temporary Excavations
<br />7.17.1 Excavations up to 5 feet in height may be required during grading and construction operations.
<br />The excavations are expected to expose artificial fill and alluvial soils, which are suitable for
<br />vertical excavations up to 5 feet in height where loose soils or caving sands are not present,
<br />and where not surcharged by adjacent traffic or structures.
<br />7.17.2 Vertical excavations greater than 5 feet or where surcharged by existing structures will require
<br />sloping or shoring measures in order to provide a stable excavation. Where sufficient space is
<br />available, temporary unsurcharged embankments could be sloped back at a uniform 1:1 slope
<br />gradient or flatter up to a maximum height of 10 feet. A uniform slope does not have a vertical
<br />portion.
<br />7.17.3 If excavations in close proximity to an adjacent property line and/or structure are required,
<br />special excavation measures such as slot -cutting or shoring may be necessary in order to
<br />maintain lateral support of offsite improvements. Recommendations for slot cutting are
<br />provided in Section 7.18 of this report.
<br />Geocon Project No. A9799-88-01
<br />-27-
<br />June 7, 2022
<br />7.17.4 Where temporary construction slopes are utilized, the top of the slope should be barricaded to
<br />prevent vehicles and storage loads at the top of the slope within a horizontal distance equal to
<br />the height of the slope. If the temporary construction slopes are to be maintained during the
<br />rainy season, berms are suggested along the tops of the slopes where necessary to prevent
<br />runoff water from entering the excavation and eroding the slope faces. Geocon personnel
<br />should inspect the soils exposed in the cut slopes during excavation so that modifications of
<br />the slopes can be made if variations in the soil conditions occur. All excavations should be
<br />stabilized within 30 days of initial excavation.
<br />7.18 Slot Cutting
<br />7.18.1 The slot -cutting employs method s the earth as a buttress and allows the earth excavation to
<br />p Y
<br />proceed in phases. Where slot -cutting is used for foundation construction, the proposed
<br />construction techniques should be discussed with the structural engineer so that appropriate
<br />modifications can be made to the foundation design, such as additional reinforcing or details
<br />for doweling.
<br />7.18.2 It is recommended that the initial temporary excavation along the property line be sloped back
<br />at a uniform 1:1 (H:V) slope gradient or flatter for excavation of the existing soils to the
<br />necessary depth. The temporary excavation should not extend below the surcharge area of any
<br />adjacent foundations. The surcharge area may be defined by a 1:1 projection down and away
<br />from the bottom of an existing foundation. The temporary slope may then be excavated using
<br />the slot -cutting (see illustration below).
<br />Geocon Project No. A9799-88-01 - 28 - June 7, 2022
<br />7.12.6 The performance of pavement is highly dependent on providingpositive surface drainage
<br />away from the edge of the pavement. Ponding of water on or adjacent to the pavement will
<br />likely result in pavement distress and subgrade failure. Drainage from landscaped areas should
<br />be directed to controlled drainage structures. Landscape areas adjacent to the edge of asphalt
<br />pavements are not recommended due to the potential for surface or irrigation water to infiltrate
<br />the underlying permeable aggregate base and cause distress. Where such a condition cannot
<br />be avoided, consideration should be given to incorporating measures that will significantly
<br />reduce the potential for subsurface water migration into the aggregate base. If planter islands
<br />are planned, the perimeter curb should extend at least 6 inches below the level of the base
<br />materials.
<br />7.13 Retaining Wall Design
<br />7.13.1 The recommendations presented below are generally applicable to the design of rigid concrete
<br />or masonry retaining walls having a maximum height of 5 feet. In the event that walls
<br />significantly higher than 5 feet are planned, Geocon should be contacted for additional
<br />recommendations.
<br />7.13.2 Retaining wall foundations may be designed in accordance with the recommendations
<br />provided in the Foundation Design section of this report (see Section 7.6).
<br />7.13.3 Retaining walls with a level backfill surface that are not restrained at the top should be
<br />designed utilizing a triangular distribution of pressure (active pressure) of 30 pcf.
<br />7.13.4 Restrained walls are those that are not allowed to rotate more than 0.001H (where H equals
<br />the height of the retaining portion of the wall in feet) at the top of the wall. Where walls are
<br />restrained from movement at the top, walls may be designed utilizing a triangular distribution
<br />of pressure (at -rest pressure) of 65 pcf.
<br />7.13.5 The wall pressures provided above assume that the proposed retaining walls will support
<br />relatively undisturbed alluvial soils or engineered fill derived from onsite soils. If import soil
<br />will be used to backfill proposed retaining walls, revised earth pressures may be required to
<br />account for the geotechnical properties of the import soil used as engineered fill. This should
<br />be evaluated once the use of import soil is established. All imported fill shall be observed,
<br />tested, and approved by Geocon West, Inc. prior to bringing soil to the site.
<br />7.13.6 The wall pressures provided above assume that the retaining wall will be properly drained
<br />preventing the buildup of hydrostatic pressure. If retaining wall drainage is not implemented,
<br />the equivalent fluid pressure to be used in design of undrained walls is 95 pcf. The value
<br />includes hydrostatic pressures plus buoyant lateral earth pressures.
<br />Geocon Project No. A9799-88-01
<br />-25-
<br />June 7, 2022
<br />7.13.7 Additional active pressure should be added for a surcharge condition due to sloping ground,
<br />vehicular traffic or adjacent structures and should be designed for each condition as the project
<br />progresses.
<br />7.14 Retaining Wall Drainage
<br />7.14.1 Retaining walls not designed for hydrostatic pressures should be provided with a drainage
<br />system extended at least two-thirds the height of the wall. At the base of the drain system, a
<br />subdrain covered with a minimum of 12 inches of gravel should be installed, and a compacted
<br />fill blanket or other seal placed at the surface (see Figure 5). The clean bottom and subdrain
<br />pipe, behind a retaining wall, should be observed by the Geotechnical Engineer (a
<br />representative of Geocon), prior to placement of gravel or compacting backfill.
<br />7.14.2 As an alternative, a plastic drainage composite such as Miradrain or equivalent may be
<br />installed in continuous, 4-foot-wide columns along the entire back face of the wall, at 8 feet
<br />on center. The top of these drainage composite columns should terminate approximately
<br />18 inches below the ground surface, where either bardscape or a minimum of 18 inches of
<br />relatively cohesive material should be placed as a cap (see Figure 6).
<br />7.14.3 Subdrainage pipes at the base of the retaining wall drainage system should outlet to an
<br />acceptable location via controlled drainage structures. Drainage should not be allowed to flow
<br />uncontrolled over descending slopes.
<br />7.14.4 Moisture affecting below grade walls is one of the most common post -construction
<br />complaints. Poorly applied or omitted waterproofing can lead to efflorescence or standing
<br />water. Particular care should be taken in the design and installation of waterproofing to avoid
<br />moisture problems, or actual water seepage into the structure through any normal shrinkage
<br />cracks which may develop in the concrete walls, floor slab, foundations and/or construction
<br />joints. The design and inspection of the waterproofing is not the responsibility of the
<br />geotechnical engineer. A waterproofing consultant should be retained in order to recommend
<br />a product or method, which would provide protection to subterranean walls, floor slabs and
<br />foundations.
<br />7.15 Elevator Pit Design
<br />7.15.1 The elevator pit slab and retaining wall should be designed by the project structural engineer.
<br />Elevator pit walls may be designed in accordance with the recommendations in the Foundation
<br />Design and Retaining Wall Design sections of this report (see Sections 7.6 and 7.13).
<br />7.15.2 Additional active pressure should be added for a surcharge condition due to sloping ground,
<br />vehicular traffic or adjacent foundations and should be designed for each condition as the
<br />project progresses.
<br />Geocon Project No. A9799-88-01 - 26 - June 7, 2022
<br />7.11.4 Asphalt concrete should conform to Section 203-6 of the "Standard Specifications for Public
<br />Works Construction " (Green Book). Class 2 aggregate base materials should conform to
<br />Section 26-1.02A of the "Standard Specifications of the State of California, Department
<br />of Transportation " (Caltrans). The use of Crushed Miscellaneous Base (CMB) in lieu of Class
<br />2 aggregate base is acceptable. Crushed Miscellaneous Base should conform to Section
<br />200-2.4 of the "Standard Specifications for Public Works Construction " (Green Book).
<br />7.11.5 Unless specifically designed and evaluated by the project structural engineer, where exterior
<br />concrete paving will be utilized for support of vehicles, it is recommended that the concrete
<br />be a minimum of 6 inches of concrete reinforced with No. 3 steel reinforcing bars placed
<br />18 inches on center in both horizontal directions. Concrete paving supporting vehicular traffic
<br />should be underlain by a minimum of 4 inches of aggregate base and a properly compacted
<br />subgrade. The subgrade and base material should be compacted to 95 percent relative
<br />compaction, as determined by ASTM Test Method D 1557 (latest edition).
<br />7.11.6 The performance of pavements is highly dependent upon providing positive surface drainage
<br />away from the edge of pavements. Ponding of water on or adjacent to the pavement will likely
<br />result in saturation of the subgrade materials and subsequent cracking, subsidence and
<br />pavement distress. If planters are planned adjacent to paving, it is recommended that the
<br />perimeter curb be extended at least 12 inches below the bottom of the aggregate base to
<br />minimize the introduction of water beneath the paving.
<br />7.12 Vehicular Rated Concrete Paver Recommendations
<br />7.12.1 The following recommendations are based on an assumed R-Value of 20. Once site grading
<br />activities are complete and prior to placing pavement, an R-Value should be obtained by
<br />laboratory testing to confirm the properties of the soils serving as paving subgrade.
<br />7.12.2 We calculated the paver sections in general conformance with the Caltrans Method ofFlexible
<br />Pavement Design (Highway Design Manual, Section 608.4) using an estimated Traffic Indices
<br />(TI). The project civil engineer and owner should review the pavement designations to
<br />determine appropriate locations for pavement thickness. Based on the Interlocking Concrete
<br />Pavement Institute (ICPI), the pavers should possess a minimum thickness of 3f/8 inches
<br />overlying 1 to 1'/2 inch of sand. In addition, the pavers should be installed in a pattern
<br />acceptable for vehicular traffic. It is anticipated that base materials will be used for the paver
<br />underlayment. The pavers are for decorative purposes and will not be installed for stormwater
<br />management. The table below presents the recommended concrete -unit paver sections.
<br />Geocon Project No. A9799-88-01
<br />-23-
<br />RECOMMENDED CONCRETE UNIT PAVER SECTIONS
<br />June 7, 2022
<br />Equivalent
<br />Estimated
<br />Traffic
<br />Paver Asphalt
<br />Sand
<br />Min. Aggregate
<br />Location
<br />Index
<br />Concrete
<br />Thickness
<br />Base Thickness
<br />Thickness"
<br />(inches)
<br />(inches)
<br />(inches)
<br />Automobile Parking
<br />and Driveways
<br />4.0
<br />3'/8
<br />1 - 1 %2
<br />7.0
<br />Trash Truck &
<br />7.0
<br />3'/s
<br />1 - 1 %z
<br />13.5
<br />Fire Lanes
<br />" indicates estimated value
<br />7.12.3 Prior to placing base materials, the subgrade should be scarified to a depth of approximately
<br />12 inches, moisture conditioned to near optimum moisture content, and compacted to a dry
<br />density of at least 95 percent of the laboratory maximum dry density as determined by ASTM
<br />D 1557. Similarly, the base materials should be compacted to a dry density of at least 95
<br />percent of the laboratory maximum dry density at or slightly above optimum moisture content.
<br />7.12.4 Although the pavers are not intended for stormwater infiltration, consideration should be given
<br />to installing a subdrain for the paver sections. The subdrain could be placed at the bottom of
<br />the base section below the pavers and the soil subgrade should be graded to allow water to
<br />flow to a subdrain. The subdrain should run the distance of the paver area to reduce the
<br />potential for water to build up within the paving section. The drain should be connected to an
<br />approved drainage device. The drain should consist of a 3-inch diameter perforated Schedule
<br />40, PVC pipe and placed at the bottom of the base materials.
<br />7.12.5 The pavers should be installed and maintained in accordance with the manufacturer's
<br />recommendations. Future property owners should be made aware and responsible for the
<br />maintenance program. In addition, pavers tend to shift vertically and horizontally during the
<br />life of the pavement and should be expected. The pavers normally require a concrete border to
<br />prevent lateral movement from traffic. The concrete border surrounding the pavers should be
<br />embedded at least 6 inches from finish grade surface to reduce the potential for water migration
<br />to the adjacent landscape areas and pavement areas. The pavers should be placed tightly
<br />adjacent to each other and the spacing between the paver units should be filled with appropriate
<br />filler. A polymer sand (Poly -Sand) can be used on the non -storm water quality paver area to
<br />help prevent water infiltration.
<br />Geocon Project No. A9799-88-01 - 24 - June 7, 2022
<br />7.10.3 Slabs -on -grade at the ground surface that may receive moisture -sensitive floor coverings or
<br />may be used to store moisture -sensitive materials should be underlain by a vapor retarder
<br />placed directly beneath the slab. The vapor retarder and acceptable permeance should be
<br />specified by the project architect or developer based on the type of floor covering that will be
<br />installed. The vapor retarder design should be consistent with the guidelines presented in
<br />Section 9.3 of the American Concrete Institute's (ACI) Guide for Concrete Slabs that Receive
<br />Moisture -Sensitive Flooring Materials (ACI 302.2R-06) and should be installed in general
<br />conformance with ASTM E 1643 (latest edition) and the manufacturer's recommendations.
<br />A minimum thickness of 15 mils extruded polyolefm plastic is recommended; vapor retarders
<br />which contain recycled content or woven materials are not recommended. The vapor retarder
<br />should have a permeabce of less than 0.01 perms demonstrated by testing before and after
<br />mandatory conditioning. The vapor retarder should be installed in direct contact with the
<br />concrete slab with proper perimeter seal. If the California Green Building Code requirements
<br />apply to this project, the vapor retarder should be underlain by 4 inches of clean aggregate.
<br />It is important that the vapor retarder be puncture resistant since it will be in direct contact
<br />with angular gravel. As an alternative to the clean aggregate suggested in the Green Building
<br />Code, it is our opinion that the concrete slab -on -grade may be underlain by a vapor retarder
<br />over 4 inches of clean sand (sand equivalent greater than 30), since the sand will serve a
<br />capillary break and will minimize the potential for punctures and damage to the vapor barrier.
<br />7.10.4 For seismic design purposes, a coefficient of friction of 0.35 may be utilized between concrete
<br />slabs and subgrade soils without a moisture barrier, and 0.15 for slabs underlain by a moisture
<br />barrier.
<br />7.10.5 Exterior slabs for walkways or flatwork, not subject to traffic loads, should be at least
<br />4 inches thick and reinforced with No. 3 steel reinforcing bars placed 18 inches on center in
<br />both horizontal directions, positioned near the slab midpoint. Prior to construction of slabs, the
<br />upper 12 inches of subgrade should be moisture conditioned to near optimum moisture content
<br />and properly compacted to at least 95 percent relative compaction, as determined by ASTM
<br />Test Method D 1557 (latest edition). Crack control joints should be spaced at intervals not
<br />greater than 10 feet and should be constructed using saw -cuts or other methods as soon as
<br />practical following concrete placement. Crack control joints should extend a minimum depth
<br />of one-fourth the slab thickness. Construction joints should be designed by the project
<br />structural engineer.
<br />Geocon Project No. A9799-88-01
<br />-21-
<br />June 7, 2022
<br />7.10.6 The recommendations of this report are intended to reduce the potential for cracking of slabs
<br />due to settlement. However, even with the incorporation of the recommendations presented
<br />herein, foundations, stucco walls, and slabs -on -grade may exhibit some cracking due to minor
<br />soil movement and/or concrete shrinkage. The occurrence of concrete shrinkage cracks is
<br />independent of the supporting soil characteristics. Their occurrence may be reduced and/or
<br />controlled by limiting the slump of the concrete, proper concrete placement and curing, and
<br />by the placement of crack control joints at periodic intervals, in particular, where re-entrant
<br />slab corners occur.
<br />7.11 Preliminary Pavement Recommendations
<br />7.11.1 Where new paving is to be placed, it is recommended that all existing fill and soft alluvium
<br />materials be excavated and properly compacted for paving support. The client should be aware
<br />that excavation and compaction of all existing artificial fill and soft alluvium in the area of
<br />new paving is not required; however, paving constructed over existing uncertified fill or
<br />unsuitable alluvium material may experience increased settlement and/or cracking, and may
<br />therefore have a shorter design life and increased maintenance costs. As a minimum, the upper
<br />12 inches of paving subgrade should be scarified, moisture conditioned to near optimum
<br />moisture content, and properly compacted to at least 95 percent relative compaction, as
<br />determined by ASTM Test Method D 1557 (latest edition).
<br />7.1.1.2 The following pavement sections are based on an assumed R-Value of 20. Once site grading
<br />activities are complete an R-Value should be obtained by laboratory testing to confirm the
<br />properties of the soils serving as paving subgrade, prior to placing pavement.
<br />7.11.3 The Traffic Indices listed below are estimates. Geocon does not practice in the field of traffic
<br />engineering. The actual Traffic Index for each area should be determined by the project civil
<br />engineer. If pavement sections for Traffic Indices other than those listed below are required,
<br />Geocon should be contacted to provide additional recommendations. Pavement thicknesses
<br />were determined following procedures outlined in the California Highway Design Manual
<br />(Caltrans). It is anticipated that the majority of traffic will consist of automobile and large
<br />truck traffic.
<br />PRELIMINARY PAVEMENT DESIGN SECTIONS
<br />Location
<br />Estimated Traffic
<br />Asphalt Concrete
<br />Class 2 Aggregate
<br />Index (TI)
<br />(inches)
<br />Base (inches)
<br />Automobile Parking
<br />and Driveways
<br />4.0
<br />3.0
<br />4.0
<br />Trash Truck &
<br />Fire Lanes
<br />7.0
<br />4.0
<br />12.0
<br />Geocon Project No. A9799-88-01
<br />-22-
<br />June 7, 2022
<br />Architecture + Planning
<br />17911 Von Karman Ave.
<br />Suite 200
<br />Irvine, CA 92614
<br />ktgy.com
<br />949.851.2133
<br />KTGY Project No: 2017-0934
<br />Project Contact: Debbie Holland
<br />Email: dholland@ktgy.com
<br />Principal: Wil Wong
<br />Project Designer: D. Schoolmeester
<br />Project Director: Debbie Holland
<br />Developer
<br />ED OAK
<br />INVLS"I'NAEN'I'S
<br />4199 CAMPUS DRIVE
<br />IRVI NE, CA 92612
<br />PHONE NO. (714) 342-2502
<br />TF
<br />r
<br />N
<br />Cn
<br />Q
<br />U
<br />Q
<br />Z
<br />Q
<br />Q
<br />Z
<br />�Q
<br />U)
<br />W
<br />W
<br />U)
<br />W
<br />Ln
<br />Ln
<br />06
<br />LO
<br />V_
<br />No. Date Description H_C
<br />G
<br />00
<br />D
<br />U)
<br />IseO
<br />W
<br />2
<br />U
<br />Z
<br />Q
<br />J
<br />It is the clients responsibility prior to or during construction to notify the architect in writing
<br />of any perceived errors or omissions in the plans and specifications of which a contractor
<br />thoroughly knowledgeable with the building codes and methods of construction should
<br />reasonably be aware. Written instructions addressing such perceived errors or omissions
<br />shall be received from the architect prior to the client or clients subcontractors proceeding
<br />with the work. The client will be responsible for any defects in construction if these
<br />procedures are not followed.
<br />v,
<br />S�D ARcj,11
<br />ILL
<br />N
<br />No. C29795
<br />0
<br />RENEWAL DATE
<br />AUGUST 31, 2023
<br />qTF OF
<br />0
<br />C��
<br />A
<br />License Stamp
<br />o
<br />GEOTECHNICAL
<br />REPORT
<br />COPYRIGHT (c
<br />AO-83
<br />
|