Example Schedule
<br />City of Lompoc
<br />Proposal
<br />forCor_ction Mangement & Inspection Services
<br />Lompoc Landfill Drainage Improvements
<br />PRELIM INARY CONSTRUCTION SCHEDULE
<br />ID
<br />Task Name
<br />Duration
<br />tart Finish Predecesmrs Cos[
<br />Feb Mar Ann May Jun Jul AUR Sep Oc[
<br />1
<br />Lompoc Landfill Drainage Improvements, City Project No.
<br />155 days
<br />Mon 3/20/23 Fri 10/20/23
<br />$5,202,954.00
<br />FY-20-LF-1 jRFP-20.LF-lb)
<br />2
<br />***City Executes Construction Management Contract***
<br />0days
<br />Mon 3/20/23 Mon 3/20/23
<br />$0.00
<br />31M
<br />3
<br />Pre -Construction Services
<br />20 days
<br />Mon 3/20/23 Fri4/14/23
<br />$0.00
<br />4
<br />Submittal Preparation
<br />10 days
<br />Mon 3/20/23 Fri 3/31/23 2
<br />$0.00
<br />5
<br />Submittal Re view
<br />Construction
<br />30 days
<br />125 days
<br />Mon 4/3/23 Fri 4/14/23 4
<br />Mon 4/17/23 Fri 10/6/23
<br />$0.00
<br />$5,202,954.00
<br />6
<br />7
<br />*•*City Issues Notice To Proceed`*"
<br />1-Mobilization/Demobilization
<br />0days
<br />3days
<br />Mon 4/17/23 Mon 4/17/235
<br />Mon 4/17/23 Wed 4/19/23 7
<br />$0.00
<br />$500,000.00
<br />4117
<br />8
<br />9
<br />2- Layout of Work Surveys
<br />3- Clearing, Grubbing, and Stripping
<br />Iday
<br />2days
<br />Thu 4/20/23 Thu 4/20/23 8
<br />Fri 4/21/23 Mon 4/24/23 9
<br />$30,000.00
<br />$I8,D00.00
<br />10
<br />11
<br />4-Excavation
<br />2days
<br />Thu 5/25/23 Fri 5/26/23 39
<br />$52,800.00
<br />12
<br />5-Earthfi11
<br />6days
<br />Mon 5/29/23 Mon 6/5/23 11
<br />$528,000.00
<br />13
<br />6-24-Inch HOPE Downdreins
<br />7-I8-Inch CPE
<br />2days
<br />Iday
<br />Tue 6/6/23 Wed 6/7/23 12
<br />Thu 6/8/23 Thu 6/8/23 13
<br />$40,940.00
<br />$10,140.00
<br />14
<br />15
<br />8-24-Inch CPE
<br />Iday
<br />Fri 6/9/23 Fri 6/9/23 14
<br />$11,960.00
<br />16
<br />9-36-Inch CPE
<br />8days
<br />Mon 6/12/23 Wed 6/21/2315
<br />$199,800.00
<br />17
<br />10-48-Inch CPE
<br />11-60-Inch CPE
<br />5days
<br />4days
<br />Thu 6/22/23 Wed 6/28/2316
<br />Thu 6/29/23 Tue 7/4/23 17
<br />$168,960.00
<br />$174,800.00
<br />'..
<br />18
<br />19
<br />12-48-Inch CMP
<br />Iday
<br />Tue 4/25/23 Tue 4/25/23 10
<br />$22,400.00
<br />20
<br />13-72-Inch Diameter CMP Vertical Standpipe
<br />14-Type l Crimp Inlet
<br />Iday
<br />Iday
<br />Wed 4/26/23 Wed 4/26/23 19
<br />Wed 7/5/23 Wed 7/5/23 18
<br />$3,800.00
<br />$21,000.00
<br />21
<br />22
<br />I5-Type 2 Drop Inlet
<br />16-CPE Flare Inlet
<br />2days
<br />Iday
<br />Thu 7/6/23 Fri 7/7/23 21
<br />Mon 7/10/23 Mon 7/10/2322
<br />$27,600.00
<br />$5,400.00
<br />23
<br />24
<br />17-Manhole
<br />18- Concrete Lined 1'V-Ditch Channel
<br />Iday
<br />3days
<br />Tue 7/11/23 Tue 7/11/23 23
<br />Wed 7/12/23 Fri 7/14/23 24
<br />$24,000.00
<br />$44,850.00
<br />25
<br />26
<br />19-Concrete Lined l.5'V-Ditch Channel
<br />14 days
<br />Mon 7/17/23 Thu 8/3/23 25
<br />$402,300.00
<br />27
<br />20- Concrete Lined 2'V-Ditch Channel
<br />12 days
<br />Fri 8/4/23 Mon 8/21/2326
<br />$453,750.00
<br />28
<br />21- Concrete Lined Trapezoidal Channel
<br />11 days
<br />Tue 8/22/23 Tue 9/5/23 27
<br />$486,000.00
<br />29
<br />22-RPP Lined V-Ditch Channel
<br />5days
<br />Wed 9/6/23 Tue 9/12/23 28
<br />$194,000.00
<br />30
<br />23- RPP Lined Trapezoidal Channel
<br />Iday
<br />Wed 9/13/23 Wed 9/13/2329
<br />$55,D00DO
<br />'..
<br />31
<br />24- Erosion Control Mat Lined V-Ditch Channel
<br />3days
<br />Thu 9/14/23 Mon 9/18/2330
<br />$149,600.00
<br />32
<br />25- Erosion Control Mat Lined TrapezoidalChannel
<br />Iday
<br />Tue 9/19/23 Tue 9/19/23 31
<br />$55,650.00
<br />33
<br />26- Low Flow WaterCrossing
<br />Iday
<br />Thu 9/28/23 Thu 9/28/23 34
<br />$29,520.Do
<br />34
<br />27- Type 2 Drop Inlet Splash Wall Structures
<br />28- Basin Outlet Pipe Structure (Splash Wall)
<br />6days
<br />2days
<br />Wed 9/20/23 Wed 9/27/2332
<br />Thu 4/27/23 Fri 4/28/23 20
<br />$21,600.00
<br />$28,DDO.00
<br />35
<br />36
<br />29-Sediment and Erosion Control DuringConstruction
<br />125 days
<br />Mon 4/17/23 Fri 10/6/23 7
<br />$48,D00.00
<br />37
<br />30- Paved Road Crossing
<br />31-Hydroseeding
<br />2days
<br />2days
<br />Fri 9/29/23 Mon 10/2/2333
<br />Thu 10/5/23 Fri 10/6/23 45
<br />$27,170.00
<br />$28,D00.00
<br />It
<br />38
<br />39
<br />32- Landfill Gas Header Relocation
<br />3days
<br />Mon 5/22/23 Wed 5/24/2350
<br />$16,500.00
<br />'..
<br />m
<br />33- Fair Cloth Skimmer
<br />Iday
<br />Mon 5/1/23 Mon 5/1/23 35
<br />$22,Do0.00
<br />'..
<br />41
<br />34-Retaining Wall
<br />4days
<br />Tue 5/2/23 Fri 5/5/23 40
<br />$351,000.00
<br />42
<br />35- Existing Fence Removal
<br />Iday
<br />Mon 5/8/23 Mon 5/8/23 41
<br />$1,920.D0
<br />43
<br />36- Fence Installation
<br />Iday
<br />Tue 5/I6/23 ITue 5/16/23 47
<br />$7,2DO.00
<br />44
<br />37-4-Inch Thick Shotcrete
<br />Iday
<br />Tue 5/9/23 Tue 5/9/23 42
<br />$78,650.00
<br />45
<br />38-Asphalt Paving
<br />2days
<br />Tue 10/3/23 Wed 10/4/2337
<br />$204,600.00
<br />46
<br />39-8-Inch Thick Reinforced Concrete
<br />3days
<br />Wed 5/10/23 Fri 5/12/23 44
<br />$303,240.00
<br />47
<br />40- Geogrid Slope Reinforcement
<br />Iday
<br />Mon 5/I5/23 Mon 5/15/2346
<br />$70,980.00
<br />48
<br />41- Fire Hydrant and Water Supply Relocation
<br />Iday
<br />Tue 5/16/23 Tue 5/16/23 47
<br />$18,DOO.00
<br />09
<br />42-Well Decommissioning
<br />Iday
<br />Wed 5/17/23 Wed 5/17/2348
<br />$32,D00.00
<br />50
<br />43- Power Pole Relocation
<br />2days
<br />Thu 5/18/23 Fri 5/19/23 49
<br />$22,000.00
<br />51
<br />44- Concrete Block Outfall Structure at Olive Avenue
<br />5days
<br />Fri 9/29/23 Thu 10/5/23 33
<br />$40,DOO.00
<br />52
<br />45- Storm Drain Repair Fill
<br />10 days
<br />Thu 4/20/23 Wed 5/3/23 8
<br />$181,824.00
<br />10/6
<br />53
<br />*'*Construction Complete*** 0days Fri 10/6/23 Fri 10/6/23 38,36,51,52 $0.00
<br />Post-Construcfion Services 10 days Mon 10/9/23 Fri 10/20/23 153 $0.00
<br />54
<br />Page 1