Laserfiche WebLink
ITEM 1.2 REVISED MWD CONNECTION <br /> TE0 <br /> Roberts <br /> INCORPORATED <br /> Santa Ana Request: Following submittal and approval of redesigned connection,TER ordered materials and will re-mobilize. Five working <br /> days are proposed to complete the revised scope of work which includes: <br /> Mobilization <br /> Excavation&Shoring <br /> Installation of Redesigned Piping <br /> Additional Welding <br /> Additional Confined Space Entry <br /> Additional Ground Water Mitigation <br /> Additional Traffic Control <br /> Additional Restoration <br /> See work sheet&WCP Quote <br /> Estimated Cost Total <br /> Item 1.2 Request$102,761.64 <br /> Combiined Change Order Requesto <br /> Item 1.1 Request$55,773.01 <br /> Item 1.2 Request$102,761.64 <br /> Total$158,534.65 <br /> City Council 10 —44 5/21/2024 <br />