The unit price for each Install Electrical Meter Pedestal shall be considered full compensation for
<br /> furnishing all labor, materials,tools, equipment, removals,paving, landscape repair, irrigation
<br /> repair, root shaving, sidewalk restoration, and appurtenances for all related items of work
<br /> necessary for the installation.No additional compensation will be allowed therefore.
<br /> Item No. 5—Install 2" PVC Conduit
<br /> This work consists of furnishing and installing Polyvinylchloride (PVC) street lighting conduit
<br /> including pull tape, ground wire, fittings, duct seal, utility potholing, concrete or asphalt
<br /> restoration and appurtenances complete and in place,of the size indicated on the plans.
<br /> The unit price bid per linear foot of PVC Conduit shall be considered full compensation for
<br /> furnishing all labor, materials,tools, equipment, removals,paving, landscape repair, irrigation
<br /> repair, root shaving, sidewalk restoration, pothole and/or trench backfill per City Std. Plan 1150,
<br /> permanent asphalt replacement, permanent PCC replacement, striping and appurtenances for all
<br /> related items of work necessary for the installation.No additional compensation will be allowed
<br /> therefore.
<br /> Item No. 6—Install No. 5 Pull Box
<br /> This work consists of furnishing and installing and/or replacing pull box including Concrete Lid,
<br /> the removal and/or modification of any interfering portions of existing pull box, conduit, PCC,
<br /> concrete and asphalt restoration, as indicated on plans and directed by the Engineer.
<br /> The unit price for each Pull Box shall be considered full compensation for furnishing all labor,
<br /> materials,tools, equipment, removals,paving, landscape repair, irrigation repair,root shaving,
<br /> sidewalk restoration, and appurtenances for all related items of work necessary for the
<br /> installation. No additional compensation will be allowed therefore.
<br /> Item No. 7—Pothole Street Light Pole Location
<br /> Payment for Pothole Street Light Pole Location shall be considered full compensation for
<br /> furnishing all labor,materials,tools, equipment, removals, excavation,paving, landscape repair,
<br /> irrigation repair, root shaving, sidewalk restoration,pothole and trench backfill per City Std. Plan
<br /> 1150,permanent asphalt replacement,permanent PCC replacement and appurtenances for all
<br /> related items of work necessary for the installation.No additional compensation will be allowed
<br /> therefore.
<br /> Item No. 8—Traffic Control Work
<br /> The work under this item for Signing and Striping shall be in accordance with the latest Watch
<br /> Manual, CA MUTCD, Caltrans and any City Standard Specifications, plans, and/or any City's
<br /> Special Provisions/Contract Documents to be provided for each Task Order Work.
<br /> City of Santa Ana RFP 23-182
<br /> Page Al-15
<br />
|