7. For additional saw cut joints on the sidewalk along Bristol St. to prevent cracking per PCO #26 <br /> dated September 23, 2025. <br /> AGREED COST: $21,790.98 <br /> 8. To install green MMA striping for the bike lanes to increase visibility per PCO #29 dated <br /> January 13, 2026. <br /> AGREED COST: $16,573.90 <br /> 9. To upgrade the irrigation controller box to allow for a larger irrigation controller and to avoid <br /> overheating in the unit per PCO#30 dated January 22, 2026. <br /> AGREED COST: $3,348.05 <br /> 10. To install temporary traffic control in front of Santa Ana College in the southbound direction to <br /> enhance visibility and safety per PCO #31 dated February 4, 2026. <br /> AGREED COST: $5,937.34 <br /> 11. Credit to the City for using single split face block in lieu of double split face block per PCO#10 <br /> dated February 24, 2026. <br /> AGREED COST: ($10,000.00) <br /> 12. Credit to the City for installing wall cap with incorrect finish. <br /> AGREED COST: ($449.73) <br /> 13. To install crushed miscellaneous base within the lot east of Bristol St. to eliminate pollutant <br /> runoff into the storm drains per PCO#32 dated March 2, 2026. <br /> AGREED COST: $33,507.86 <br /> 14. Replace existing drive approach with sidewalk and curb and gutter to eliminate non-authorized <br /> parking and allow SCE pole improvements per the original plans per PCO #33 dated March 24, <br /> 2026. <br /> AGREED COST: $12,000.00 <br /> TOTAL AGREED COST: $139,204.15 <br /> Page 2 of 3 <br />