CITY OF SANTA ANA
<br />DEFINITION OF BID ITEMS
<br />PROJECT NO.: 25-6030
<br />TRAFFIC SIGNAL INSTALLATION AT SEGERSTROM AVENUE AND ROSEWOOD
<br />AVENUE
<br />all materials, labor, equipment, tools, and incidentals and no additional compensation will be
<br />allowed therefore.
<br />Bid Item No. 11 - Fiber Optic Splice Enclosure
<br />This work consists of installing a Corning Cable Systems Fiber Optic Splice Closure including
<br />splice trays, pigtails, connectors, and labeling as indicated on plans.
<br />Payment for the installation of Fiber Optic Splice Enclosure, shall be at contract unit price bid
<br />per Each Item listed in the Bid Proposal and shall be considered full compensation for furnishing
<br />all materials, labor, equipment, tools, and incidentals and no additional compensation will be
<br />allowed therefore.
<br />Bid Item No. 12 - Signing and Striping
<br />Removal of all traffic striping and pavement markings shall be by wet blasting. All traffic striping
<br />may be removed by wet sandblasting with the Engineer's approval, shall be completely removed
<br />to the satisfaction of the Engineer. Any damaged pavement due to pavement removal
<br />(Grinding), SHALL be repair to maintain a smooth and uniform surface. All removal areas
<br />shall be slurry sealed by rubberized slurry seal. Slurry seal shall cover from lane line to lane
<br />line unless directed otherwise by the engineer.
<br />Payment for Signing and Striping shall be at the contract unit price bid per Lump Sum listed in the
<br />Bid Proposal, and shall include full compensation for furnishing all labor, materials, tools, equipment,
<br />disposal of all removed materials and incidentals as required, and no additional compensation will be
<br />allowed therefore.
<br />Bid Item No. 13 - Pothole Pole Location for Utility Conflicts
<br />The work under this item consists of potholing for traffic signal equipment location as shown on
<br />the plans. One pothole bid item includes all utilities found in the pothole, not per utility.
<br />The work under this item consists of mobilizing the Contractor's workforce, labor, equipment,
<br />and materials; providing bonds, insurance, and license; demobilizing; and performing final
<br />cleanup. All work shall be performed to the satisfaction of the Engineer.
<br />Payment for Pothole Pole Location for Utility Conflicts shall be considered full compensation
<br />for furnishing all labor, materials, tools, equipment, removals, paving, landscape repair, irrigation
<br />repair, root shaving, sidewalk restoration, pothole and trench backfill per City Std. Plan 1150,
<br />permanent asphalt replacement, permanent PCC replacement and appurtenances for all related
<br />items of work necessary for the installation. No additional compensation will be allowed therefore.
<br />Bid Item No. 14 - Pothole Utilities Not Shown on Plan
<br />Payment for Pothole Utilities Not Shown on Plan, shall be at contract unit price bid per Each
<br />Item listed in the Bid Proposal and shall be considered full compensation for furnishing all labor,
<br />materials, tools, equipment, removals, paving, landscape repair, sidewalk restoration, pothole and
<br />Now