CITY OF SANTA ANA
<br />DEFINITION OF BID ITEMS
<br />PROJECT NO.: 25-6030
<br />TRAFFIC SIGNAL INSTALLATION AT SEGERSTROM AVENUE AND ROSEWOOD
<br />AVENUE
<br />trench backfill per City Std. Plan 1150, permanent asphalt replacement, permanent PCC
<br />replacement, and appurtenances for all related items of work necessary for the installation, and no
<br />additional compensation will be allowed therefore.
<br />Bid Item No. 15 - Unclassified Excavation
<br />Payment for this item shall be at the contract unit price bid per Cubic Yard listed in the Bid
<br />Proposal/Plans, and shall include full compensation for doing all work, including furnishing all
<br />materials, labor, equipment, tools, disposal of excavated materials, and incidentals as required and
<br />no additional compensation will be allowed therefore.
<br />Payment for unclassified fill, if any, is considered as included in the unit price paid for unclassified
<br />excavation.
<br />Payment for over -excavation shall be paid for at the unit price for unclassified excavation.
<br />Bid Item No. 16 - AC Pavement
<br />Payment for this item shall be at the contract unit price bid per Ton as listed in the Bid Proposal,
<br />and shall include full compensation for doing all work; including furnishing all materials, labor,
<br />equipment, tools, and incidentals as required and no additional compensation will be allowed
<br />therefore.
<br />Payment for asphalt concrete pavement used in areas of over -excavation to mitigate unsuitable
<br />subgrade materials shall be paid for at the contract unit price bid per ton.
<br />Bid Item No. 17 - PCC Sidewalk (T=4")
<br />The work under this item consists of grading, compacting subgrade, and constructing 4-inch thick
<br />Stamped Colored PCC Sidewalk in accordance with the provisions of Section 301-1, "Subgrade
<br />Preparation," and Section 303-5, "Concrete Curbs, Walks, Gutters, Cross Gutters, Alley Intersections,
<br />Access Ramps, and Driveways," of the Standard Specifications, plans, and contract document
<br />specifications.
<br />Payment for this item shall be at the contract unit price bid per Square Foot as listed in the Bid
<br />Proposal/Plans, and shall include full compensation for doing all work, including furnishing all
<br />materials, labor, equipment, tools, and incidentals as required and no additional compensation will
<br />be allowed therefore. Payment for thickness (T=6") shall be paid 1.5 times the unit price.
<br />Bid Item No. 18 - PCC Median 4" Stamped Concrete
<br />The work under this item consists of grading, compacting subgrade, and constructing 4-inch
<br />thick PCC Sidewalk in accordance with the provisions of Section 301-1, "Subgrade Preparation,"
<br />and Section 303-5, "Concrete Curbs, Walks, Gutters, Cross Gutters, Alley Intersections, Access
<br />Ramps, and Driveways," of the Standard Specifications, plans, and contract document
<br />specifications.
<br />5 of 8
<br />
|