CITY OF SANTA ANA
<br />DEFINITION OF BID ITEMS
<br />PROJECT NO.: 25-6030
<br />TRAFFIC SIGNAL INSTALLATION AT SEGERSTROM AVENUE AND ROSEWOOD
<br />AVENUE
<br />Bid Item No. 22 - PCC Modified Retaining Curb
<br />The work under this item consists of grading, compacting subgrade, and constructing PCC Modified
<br />Retaining Curb in accordance with the provisions of Section 301-1, "Subgrade Preparation," and
<br />Section 303-5, "Concrete Curb, Walks, Gutters, Cross Gutters, Alley Intersections, Access Ramps,
<br />and Driveways," of the Standard Specifications, plans, and contract document specification.
<br />Payment for this item shall be at the contract unit price bid per Linear Foot as listed in the Bid
<br />Proposal, and shall include full compensation for doing all work; including furnishing all materials,
<br />labor, equipment, tools, and incidentals as required and no additional compensation will be allowed
<br />therefor.
<br />Bid Item No. 23 - PCC Modified Retaining Curb (Double)
<br />The work under this item consists of grading, compacting subgrade, and constructing PCC Modified
<br />Retaining Curb (Double) in accordance with the provisions of Section 301-1, "Subgrade Preparation,"
<br />and Section 303-5, "Concrete Curb, Walks, Gutters, Cross Gutters, Alley Intersections, Access
<br />Ramps, and Driveways," of the Standard Specifications, plans, and contract document specification.
<br />Payment for this item shall be at the contract unit price bid per Linear Foot as listed in the Bid
<br />Proposal, and shall include full compensation for doing all work; including furnishing all materials,
<br />labor, equipment, tools, and incidentals as required and no additional compensation will be allowed
<br />therefor.
<br />Bid Item No. 24 - PCC Curb Ramp
<br />The work under this item consists of grading, compacting subgrade, and constructing 4-inch thick
<br />PCC Curb Ramp including curb & gutter in accordance with the provisions of Section 301-1,
<br />"Subgrade Preparation," and Section 303-5, "Concrete Curb, Walks, Gutters, Cross Gutters, Alley
<br />Intersections, Access Ramps, and Driveways," of the Standard Specifications and contract document
<br />specification.
<br />Payment for this item shall be at the contract unit price bid per Square Foot as listed in the Bid
<br />Proposal, and shall include full compensation for doing all work, including furnishing all materials,
<br />labor, equipment, tools, and incidentals as required and no additional compensation will be allowed
<br />therefore. The curb ramp area includes the ramp's flares and ramp area. The landing area is
<br />considered sidewalk.
<br />Bid Item No. 25 - Install Liner Along Existing 10" VCP Sewer Pipe
<br />Payment for this item shall be at the contract unit price bid per Linear Foot as listed in the Bid
<br />Proposal/Plans, and shall include full compensation for doing all work, including furnishing all
<br />materials, labor, equipment, tools, and incidentals as required and no additional compensation will
<br />be allowed therefore.