Laserfiche WebLink
CITY OF SANTA ANA <br />SPECIFICATIONS <br />PROJECT NO.: 25-6030 <br />TRAFFIC SIGNAL INSTALLATION AT SEGERSTROM AVENUE AND ROSEWOOD <br />AVENUE <br />SECTION 6 - PROSECUTIONAND PROGRESS OF THE WORK <br />6-1 CONSTRUCTION SCHEDULE AND COMMENCEMENT OF THE WORK <br />6-1.1 Construction Schedule <br />Add the following to this subsection: <br />A working day shall be defined as outlined below, and the Contractor's activities shall be confined <br />accordingly: <br />1. From 9:00 a.m. to 3:00 p.m., Monday through Friday, for work requiring temporary <br />lane closures, i.e. those having less than a 24-hour duration, and for work at major <br />intersections. As an alternative, construction at major intersections may be permitted <br />on Fridays, at night or on weekends, at the discretion of the Engineer. <br />2. From 7:00 a.m. to 5:00 p.m., Monday through Friday, within work areas having either <br />no lane closures or having continuous lane closures, i.e. 24-hour closures lasting more <br />than one day. For work in, or adjacent to, residential areas, work shall not commence <br />prior to 8:00 a.m. <br />Deviation from these hours/days shall not be permitted without the prior consent of the Engineer, <br />except in emergencies involving immediate hazard to persons or property, or as specified <br />otherwise. <br />Holidays as herein referred to shall be deemed to be: <br />• New Year's Day • Independence Day <br />• Martin Luther King Day • Labor Day <br />• President's Day • Veteran's Day <br />• Cesar Chavez Day • Thanksgiving Day and the day after <br />• Memorial Day • Christmas Eve through New Year's Day <br />In addition to the holidays listed above, the City has a holiday moratorium; refer to City of Santa <br />Ana Standard Plan No. 1160. <br />The Contractor is required to submit a comprehensive baseline schedule to the Engineer for <br />approval before commencing construction. This schedule must detail the sequence of construction <br />activities, including major milestones and critical path tasks. Throughout the construction phase, <br />the Contractor shall provide monthly updates to the baseline schedule, reflecting the current <br />progress of the project, completed tasks, work planned for the upcoming month, and any schedule <br />changes. <br />In addition to the baseline schedule and monthly updates, the Contractor shall also provide a rolling <br />3-week look -ahead schedule. This schedule should offer a detailed outlook of planned activities <br />for the upcoming three-week period, focusing on immediate work activities as well as work <br />completed in the previous week. The rolling look -ahead schedule must be submitted to the <br />17 <br />