Laserfiche WebLink
Bristol Street Improvements Project -Phase 4 <br />Public Works Agency <br />Item 17 <br />March 04, 2025 <br />Slide 8 <br />PROJECT PHASING <br />Phase 3: Wet Utilities and Civil Work <br />Wet Utilities <br />Water Main and Storm Drain <br />Civil Work <br />Sidewalk, Bus Pads, Curb & Gutter <br />Work in this phase will occur in different stages. <br />All utility and civil work on one side of the street <br />will occur first. Then on the other side of the <br />street and then lastly the center median <br />improvements. This is designed to minimize shifts <br />in traffic patterns during construction.