Laserfiche WebLink
Bristol Street Improvements Project -Phase 4 <br />Public Works Agency <br />Item 17 <br />March 04, 2025 <br />Slide 7 <br />UNDERGROUND UTILITIES <br />•Past Challenges: SCE and TELECOMs previously used their <br />own contractors underground structures. This resulted in <br />costly and time-consuming delays. <br />•Proactive Risk Management: <br />–Actively managing risk through weekly coordination meetings <br />with contractor, SCE, and TELECOMs. <br />–City’s contractor will now perform underground work <br />eliminating dependence on outside agencies and reduces risk <br />of project delays. <br />•Responsibilities of SCE & TELECOMs: Installing cabling <br />and removing power poles. <br />•SCE’s Current Status: <br />–SCE is obligated to relocate their utilities under its franchise <br />agreement with the City upon notification of a project. <br />–SCE will submit pole removal plans for permitting.