Laserfiche WebLink
Agreed Price = $10,250.27 <br /> 7. To compensate the contractor for time, materials, and equipment associated with fine grading at <br /> Lillie King Park to facilitate the new turf field per PCO #7 dated June 18, 2025. <br /> AGREED PRICE $21,345.85 <br /> 8. To compensate the contractor for a cast-in-place Reinforced Concrete Box (RCB) stormdrain on <br /> Rousselle Street near St Gertrude PI per PCO#9 dated July 16, 2025. The pre-cast RCB could <br /> not be installed per plan due to a conflict with an AT&T transcontinental duct bank. <br /> Agreed Price = $116,894.05 <br /> TOTAL AGREED PRICE = 271 579.57 <br /> Page 2 of 3 <br />