Laserfiche WebLink
Exhibit A Scope of Work—Graviton Consultant Agreement <br /> Pre-Implementation Tasks 130d 08/04/25 01/02/26 <br /> 2.2.0 Chart of Account Design 130d 07/07/25 01/02/26 <br /> Stage 1-Plan 40d 01/05/26 02/27/26 <br /> 2.1.1 Project Management Plan 20d 01/05/26 01/30/26 <br /> 2.2.1 Requirements/Use Cases/BPMs 20d 02/02/26 02/27/26 <br /> Stage 2-Design 80d 03/02/26 06/19/26 <br /> 2.2.2 Business Process Familiarization 20d 03/02/26 03/27/26 <br /> 2.3.2 CEMLI Cycle 1 40d 03/30/26 05/22/26 <br /> 2.2.3 Conference Room Pilot 1 20d 05/25/26 06/19/26 <br /> Stage 3-Build 150d 06/22/26 01/15/27 <br /> 2.3.3 CEMLI Cycle 2 40d 06/22/26 08/14/26 <br /> 2.2.4 Conference Room Pilot 2 25d 08/17/26 09/18/26 <br /> 2.3.4 CEMLI Cycle 3 40d 09/21/26 11/13/26 <br /> 2.2.5 Conference Room Pilot 3 25d 11/16/26 12/18/26 <br /> 2.1.2 Project Scope 20d 12/21/26 01/15/27 <br /> 2.1.3 Test Plan 20d 12/21/26 01/15/27 <br /> 2.5.1 End User Training Plan 20d 12/21/26 01/15/27 <br /> Stage 4-Test 140d 12/21/26 07/02/27 <br /> 2.3.5 CEMLI Cycle 4 30d 12/21/26 01/29/27 <br /> 2.2.6 System Test 40d 02/01/27 03/26/27 <br /> 2.3.6 CEMLI Cycle 5 20d 03/29/27 04/23/27 <br /> 2.2.7 User Acceptance Test 20d 04/26/27 05/21/27 <br /> 2.1.4 Cutover Plan 20d 04/26/27 05/21/27 <br /> 2.5.2 End User Training Content 60d 03/01/27 05/21/27 <br /> 2.5.3 End User Training 30d 05/24/27 07/02/27 <br /> 2.4.4 Department Readiness 30d 05/24/27 07/02/27 <br /> Stage 5-Deploy 75d 06/21/27 10/01/27 <br /> 2.3.7 Production Cutover 10d 06/21/27 07/02/27 <br /> 2.4.5 Operations Transition Plan 20d 07/05/27 07/30/27 <br /> 2.2.8 Production Support 65d 07/05/27 10/01/27 <br /> 2.1.5 Project Phase Closeout 20d 09/06/27 10/01/27 <br /> 76 GRAVITON <br />