EXHIBIT 4
<br /> Orange County Transportation Authority
<br /> FY 2025/26 - FY 2031/32 Capital Improvement Program
<br /> TIP In r.P-19674 IMPLEMENTING AGENCY Santa Ana,City of
<br /> Local Project Number: Project Title
<br /> Additional Project IDs: 24-SNTA-ECP-4092 10th and Flower Stormwater Capture Project
<br /> Type of Work: Environmental Cleanup Project Description
<br /> Type of Work Description: Environmental The City of Santa Ana proposes to install one HDS,two Catch Basin Filter Inserts,three Bioretention
<br /> Cleanup-Other Basins,and two Underground Infiltration Systems.The multi-benefit project features the installation of
<br /> stormwater BMPs,designed to capture and in
<br /> Limits FISCAL TOTAL
<br /> FUND TYPE ENG ROW CON/IMP O&M TOTAL
<br /> 10th and Flower Street YEAR ESCALATED
<br /> Project Notes 2026 Environmental Cleanup $0 $0 $600,000 $0 $600,000 $615,000
<br /> CarryProgram(ECP)-Tier 1
<br /> pending
<br /> ardreimbursements,
<br /> for active project expenditures, 2026 Other $0 $0 $750,500 $0 $750,500 $769,262
<br /> pending reimbursements,and/or final invoice.
<br /> Totals: $0 $0 $1,350,500 $0 $1,350,500 $1,384,262
<br /> Last Revised:25-00-Accepted Total Programmed:$1,350,500
<br /> TIP ID CP-125" IMPLEMENTING AGENCY Santa Ana,City of
<br /> Local Project Number: Project Title
<br /> Additional Project IDs: 1st St Traffic Safety Corridor Street Light Improvements
<br /> Type of Work: Safety Project Description
<br /> Type of Work Description: Safety-Improve Installation of Street Lights poles,LED lights,underground conduits and wiring,and new electrical
<br /> lighting of roadway meter pedestals.
<br /> Limits FISCAL TOTAL
<br /> First Street between Harbor Blvd to Susan Street
<br /> YEAR FUND TYPE ENG ROW CON/IMP O&M TOTAL ESCALATED
<br /> and First Street between Fairview Street and 2026 Measure M2 Local $5,000 $0 $270,600 $0 $275,600 $282,365
<br /> Center Street. Fairshare
<br /> Project Notes
<br /> FY 25-26 CIP Totals: $5,000 $0 $270,600 $0 $275,600 $282,365
<br /> Last Revised:25-00-Accepted Total Programmed:$275,600
<br /> TIP ID CP-12`
<br /> Local Project Number: Project Title
<br /> Additional Project IDs: Bedford Rd Rehabilitation:Main PI to North City Limit
<br /> Type of Work: Road Maintenance Project Description
<br /> Type of Work Description: Road Maintenance- Reconstruction/resurfacing of existing pavement and replacement/installation of missing or damaged,
<br /> Rehabilitation of roadway curbs,gutters,sidewalks,driveway approaches,and wheelchair ramps within this segment of
<br /> roadway.
<br /> Limits FISCAL TOTAL
<br /> Main Place to North City Limits,asphalt area only.
<br /> YEAR FUND TYPE ENG ROW CON/IMP O&M TOTAL ESCALATED
<br /> Project Notes 2025 Measure M2 Local $0 $0 $40,000 $0 $40,000 $40,000
<br /> Fairshare
<br /> Carry forward for active project expenditures. FY
<br /> 24-25 CIP;carryforward FY 23-24 amount for
<br /> active project expenditures.
<br /> Totals: $0 $0 $40,000 $0 $40,000 $40,000
<br /> Last Revised:25-00-Accepted Total Programmed:$40,000
<br /> City Council 20 — 40 3/3/2026
<br />
|