Laserfiche WebLink
EXHIBIT 2 <br /> Santa Ana Blvd. Grade Separation <br /> Table 6 - Project Milestone Preliminary Dates <br /> Begin PSRE June 2011 <br /> Complete PSRE February 2012 <br /> Begin Preliminary Engineering/Environmental June 2012 <br /> Document <br /> Complete Preliminary December 2014 <br /> Engineering/Environmental Document <br /> Begin Final Design and Right of Way April 2016* <br /> Acquisition <br /> Complete Final Design and Right of Way April 2018* <br /> Acquisition <br /> Begin Construction September 2018* <br /> Complete Construction June 2020* <br /> Complete Project Close-out December 2020* <br /> *Pending available funding <br /> 10 OTHER CONSIDERATIONS AS APPROPRIATE <br /> 10.1 Permits <br /> The potential permits are: <br /> • Orange County General NPDES Permit (SWPPP) <br /> • A Regional Water Quality Control Board (RWQCB) Permit. <br /> Cooperative Agreements and Other Agreements: <br /> • SCRRA Construction and Maintenance Agreement. <br /> • CPUC Construction Agreement. <br /> 10.2 Involvement with a Navigable Waterway <br /> There is no involvement with a Navigable Waterway within the limits of this project. <br /> 10.3 Graffiti Control <br /> The bridge and retaining wall design will include a fractured-rib finish treatment for the <br /> abutments, retaining walls, and other vertical surfaces, and this shall be constructed from <br /> the finish surface to six (6)feet above the finish surface. <br /> In addition, the columns shall be sprayed with graffiti protection, in accordance with Caltrans <br /> specifications. <br /> 10.4 Geotechnical Investigation <br /> A Geotechnical Technical Memorandum is included within this report as Attachment N, <br /> which provides preliminary information and recommendations for the improvements. During <br /> the next phase of the project, geotechnical investigation, testing, and preparation of the <br /> Final Geotechnical Report will occur. <br /> PROJECT REPORT EQUIVALENT 23 <br />