3. Approve an appropriation adjustment recognizing $2,661,975 in the Acquisition
<br /> & Development Fund, Prior Year Carryforward revenue account and appropriate
<br /> the same amount into the Acquisition & Development Fund, Improvements
<br /> Other Than Buildings expenditure account (Requires five affirmative votes).
<br /> 4. Approve an amendment to the Fiscal Year 2025-2026 Capital Improvement
<br /> Program to include an additional $4,911,975 in construction funds for the 10th
<br /> and Flower Park Project (No. 26-6642).
<br /> 5. Approve an amendment to the Fiscal Year 2025-26 Capital Improvement
<br /> Program to include an additional $300,000 in construction funds for the 10th &
<br /> Flower Park Stormwater Capture Project (No. 26-6601).
<br /> 6. Approve the Project Cost Analysis for a total estimated construction delivery cost
<br /> of $5,811,975, which includes $4,649,580 for the construction contract,
<br /> $697,437 for contract administration, inspection, and testing, and $464,958 for
<br /> unanticipated or unforeseen work.
<br /> 7. Award a construction contract to Doja, Inc., the lowest responsible bidder, in
<br /> accordance with the base bid and bid alternates in the amount of $4,649,580,
<br /> subject to change orders, for construction of the 10th and Flower Park and 10th
<br /> and Flower Stormwater Capture Projects (No. 26-6642 and 26-6601), for a term
<br /> beginning April 21, 2026 and authorize the City Manager to execute the contract.
<br /> 8. Determine that, pursuant to the California Environmental Quality Act, the
<br /> recommended actions are exempt from further review. Categorical Exemption
<br /> Environmental Review No. ER-2026-27 will be filed for Project No. 26-6642 and
<br /> 26-6601.
<br /> 18.Award a Construction Contract to Onyx Paving Company, Inc. for the
<br /> Construction of the Business Area Road Improvements at MacArthur Place
<br /> from First American Way to Columbine Avenue Project(No. 26-6700) (General
<br /> Fund)
<br /> Department(s): Public Works Agency
<br /> Recommended Action:
<br /> 1. Approve the Project Cost Analysis for a total estimated construction delivery cost
<br /> of $1,287,056, which includes $1,028,000 for the construction contract,
<br /> $156,256 for contract administration, inspection, and testing, and $102,800 for
<br /> unanticipated or unforeseen work.
<br /> 2. Award a construction contract to Onyx Paving Company, Inc., the lowest
<br /> responsible bidder, in accordance with the base bid in the amount of$1,028,000,
<br /> subject to change orders, for construction of the Business Area Road
<br /> Improvements at MacArthur Place from First American Way to Columbine
<br /> Avenue Project (No. 26-6700), for a term beginning April 21, 2026 and authorize
<br /> the City Manager to execute the contract.
<br /> CITY COUNCIL 13 APRIL 21, 2026