PROJ. NO. 116743,116415 <br />ADDENDUM NO. TWO <br />4.02 PROJECT PHASING AND LANE REQUIREMENTS <br />All Major Intersection work shall be constructed on weekend or night. <br />• Broadway at Civic Center Drive, 10"' Street, Halesworth, Washington Avenue, 17t" Street <br />and Santa Clara Avenue. <br />Segment A between Santa Clara and STA 77 +20: <br />• Phase I: All work on the west side including curb, gutter, and sidewalk. Maintain two <br />northbound through lanes at all times. Work shall be constructed on weekend or night. <br />• Phase II: All work on the east side including curb, gutter, and sidewalk. Maintain two <br />southbound through lanes at all times. <br />Segment B between STA 89+30 and Main Place Drive: <br />• Phase I: All work on the west side including curb, gutter, and sidewalk. Maintain two <br />northbound through lanes at all tunes. <br />• Phase II: All work on the east side including curb, gutter, and sidewalk. Maintain two <br />southbound through lanes and one northbound through lane at all times. Work shall be <br />constructed on weekend or night. <br />Segment C between Civic Center and Santa Clara (midblock): <br />• Phase I: All work on the west side including curb, gutter, and sidewalk. Maintain two <br />northbound tlu-ough lanes at all times. <br />• Phase II: All work on the east side including curb, gutter, and sidewalk. Maintain two <br />southbound through lanes at all times. <br />Broadway and Washington Water Main Improvements project: <br />• Maintain at least one lane in each direction on Broadway from Civic Center to Santa <br />Clara Avenue. <br />• Washington from Flower Street to Broadway can be done per WATCH. <br />Traffic control plans are required for the above. <br />