Laserfiche WebLink
Project Number Project No. 116743 and 116415 — Broadway <br />Rehabilitation and Water Main Improvements <br />CIT' OF SANTA ANA <br />PUBLIC WORKS AGENCY <br />CONTRACT CHANGE ORDER <br />Change Order Number <br />To Christensen Brothers General Enaineerina, Inc. Contractor <br />You are hereby directed to make the herein changes from the plans and specifications or do the following described work not included in the plans and specifications <br />on this contract. <br />ID[i5[�i.IF3�7.1\�[�Ixi]i1X:iEyQNIi�YY3�i►�Lf1�pLf:1»iil�L�]]'fCCx�lfi[dilg�[�7L�Hiy1��r�C\�/:fH�:# <br />Unless otherwise stated, rales for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. <br />Change requested by <br />PUBLIC WORKS AGENCY <br />8. Demolish miscellaneous PCC C&G and Sidewalk, chipping, and conduit work at five locations as <br />directed by the City of Santa Ana per PCO 92. <br />FINAL COST $18,505.47 <br />The compensation both time and cost set forth in this final change order comprises the total compensation due <br />the Contractor, all Subcontractors, and all Suppliers for all change work performed under this contract, <br />including impact on unchanged work. By signing this final change order, the Contractor acknowledges and <br />agrees on behalf of himself, all Subcontractors, and all Suppliers, that the stipulated compensation includes <br />payment for all changed work under this contract, plus all payment for interruption of schedules, extended field <br />overhead, home office overhead, profit, delay, and all impact, ripple effect or cumulative impact on all other <br />work under this Contract. The signing of this final change order constitutes full mutual accord and satisfaction <br />for all changes and work performed on this project, and that the time and cost paid per this final change order <br />constitutes the total equitable adjustments owed the Contractor, all Subcontractors, and all Suppliers for all <br />work performed on this project. The Contractor on behalf of himself, all Subcontractors, and all Suppliers <br />agrees to waive all rights, without exception or reservation of any whatsoever to file any further claim related to <br />this project. <br />TOTAL COST THIS CHANGE ORDER: DECREASE INCREASE $ 68,915.47 <br />By reason of this order the CONTRACT TIME completion will be adjusted as follows: Zero Working Days <br />We the undersigned contractor have given careful consideration to the change <br />equipment, furnish all materials, except as may otherwise be noted above, and <br />payment therefor the prices shown above. <br />Accepted, Dale { _ 3 _ IV Contractor <br />Title ' ., By <br />Approval recommended by 6 4 , <br />Approved by <br />Page 2 of 2 <br />by agree, if this proposal is approved, that we will provide all <br />necessary for the work above specified, and will accept as full <br />Inc. <br />Date <br />Date <br />