The work under this item consists of grading,compacting subgrade, constructing 12"wide by
<br /> 12"deep AC Hot Mix on compacted subgrade, and constructing PCC Curb& Gutter(outside of
<br /> the curb ramp footprint, beyond the BCR or ECR) in accordance with the provisions of Section
<br /> 301-1, "Subgrade Preparation," and Section 303-5, "Concrete Curbs, Walks, Gutters,Cross
<br /> Gutters, Alley Intersections,Access Ramps,and Driveways" and any City Standard
<br /> Specifications,plans,and/or any City's Special Provisions/Contract Documents provided by the
<br /> City for each Task Order.
<br /> Payment for PCC Curb & Gutter(A-2-8) shall be at the contract unit price bid per Linear Foot
<br /> as listed in the Fee Proposal, and shall include full compensation for doing all work, including
<br /> furnishing all materials, labor,equipment,tools, and incidentals as required and no additional
<br /> compensation will be allowed therefore.
<br /> Item No. 5-Furnish and Install New#6 Pull Box
<br /> The work under this item for Furnish and Install New#6 Pull Box shall be in accordance with
<br /> the latest CA MUTCD, Caltrans and any City Standard Specifications, plans, and/or any City's
<br /> Special Provisions/Contract Documents to be provided for each Task Order Work. The assumed
<br /> material for placement shall be concrete and any removal of an existing pull box shall be
<br /> included in the price paid to furnish and install a new pull box and no additional payment will be
<br /> allowed therefore.
<br /> Payment for Furnish and Install New#6 Pull Box shall be at the contract unit price paid per
<br /> Each as listed in the Fee Proposal, and shall include full compensation for doing all work,
<br /> including furnishing all materials, labor, equipment,tools, and incidentals as required and no
<br /> additional compensation will be allowed therefore.
<br /> Item No. 6-Adjust Manhole to Finished Grade
<br /> Payment for Adjust Manhole to Finished Grade shall be at the contract unit price bid per Each
<br /> as listed in the Fee Proposal, and shall include full compensation for doing all work, including
<br /> furnishing all materials, labor, equipment,tools, and incidentals as required and no additional
<br /> compensation will be allowed therefore.
<br /> Item No. 7-Catch Basin (Type `B,"W=10')
<br /> The work under this item consists of grading,compacting subgrade, and constructing Catch
<br /> Basin and shall be in accordance with the provisions of Section 301-1, "Subgrade Preparation,"
<br /> and Section 303-1,"Concrete Structures"and any City Standard Specifications,plans, and/or
<br /> any City's Special Provisions/Contract Documents provided by the City for each Task Order.
<br /> Payment for Catch Basin (Type "B,"W=10') shall be at the contract unit price paid per Each as
<br /> listed in the Fee Proposal, and shall include full compensation for doing all work, including
<br /> removal or replacement of existing catch basins and/or other appurtenances, including furnishing
<br /> all materials, labor, equipment,tools, and incidentals as required to construct a new catch basin,
<br /> soil preparation and compaction, and no additional compensation will be allowed therefore.
<br /> City of Santa Ana RFP 23-182
<br /> Page Al-9