and labeled control wiring, relays, and terminals along with the New M340 PLC, HMI, and Ethernet <br />Switch. <br />6) Once the control wiring is complete ICS would perform and onsite 10 check out with the city to <br />confirm everything is wired and all devices are functioning properly. The 10 list and approved <br />drawings could be used to complete this portion. <br />7) ICS would use the FAT form to create a Performance Acceptance Test (PAT) document, the city <br />and ICS would use this procedure and sign off forms to commission the site. <br />8) At commissioning, ICS would provide a binder containing all of the documentation printed as well <br />as an electronic version to turn over to the city, including old and new PLC and HMI Programs, 10, <br />and SCADA lists. <br />9) Once commission is complete, ICS could provide training to the City Operations and Maintenance <br />staff. <br />0 <br />