Chapter 3 Findings Regarding Project Alternatives Attachment "A" <br />to the Project. The construction schedule for this alternative would otherwise be similar to the <br />Project. <br />This alternative would require construction activities within and adjacent to the South Bristol <br />Street/West Segerstrom Avenue intersection; however, the duration of construction activities within <br />the intersection would be reduced to one (1) week under this alternative. Traffic control associated <br />with demolition of the existing lift station facility still would require up to two weeks; accordingly, <br />traffic control within the intersection of South Bristol Street/West Segerstrom Avenue would occur <br />for a total duration of three weeks, rather than the five weeks associated with the proposed Project. <br />In addition, this alternative would not require implementation of Construction Configurations B.1, <br />B.2, or C.1. <br />However, this alternative would require the installation of new sewer facilities beneath the existing <br />paved right -of -way of South Bristol Street that are not proposed as part of the Project (i.e., to the <br />south of the South Bristol Street/West Segerstrom Avenue intersection). The segment of South <br />Bristol Street between this site and the existing lift station facility contains a 20 -inch OCSD trunk <br />sewer, a 36 -inch MWD pipeline, a 16 -inch water main, and a SCE /MCI Duct Bank. These utilities <br />would require special support during construction of the new 18 -inch sewer, as the new sewer line <br />would need to be installed at a depth of approximately 16 feet, and this depth would increase with <br />distance from the existing facility. Construction along this segment of South Bristol Street would <br />require supporting the utilities from the top of the trench and /or the use of trench boxes /shields, <br />which would elongate the construction schedule. Due to these existing utility constraints beneath <br />South Bristol Street, portions of this roadway would need to be closed to accommodate construction <br />associated with this alternative, which has the potential to result in adverse effects to vehicular <br />circulation. Implementation of this alternative would otherwise be similar to the proposed Project <br />during construction conditions. <br />Development of a lift station at Alternative Site No. 17 would require the City to acquire private <br />property to accommodate the proposed lift station. In addition, this alternative would require the <br />City to acquire a temporary construction easement to facilitate construction of the proposed lift <br />station. <br />3.4.19.2 Summary Comparison of Environmental Effects <br />The environmental effects of constructing the proposed lift station at Alternative Site No. 17 in <br />comparison to the proposed Project site are shown in Final EIR Table 5 -1 and described in detail in <br />RDEIR Section 5.4.19. This alternative would reduce the Project's significant and unavoidable <br />impact associated with Construction Configuration C.2 by two weeks; however, this alternative <br />would create a significant and unmitigable near -term impact to the capacity of South Bristol Street <br />for a period of approximately 46 days, which is an increase in duration as compared to the twenty - <br />five (25) days of construction during which the proposed Project would create a significant <br />unavoidable impact to transportation /traffic at the South Bristol Street /West Segerstrom Avenue <br />intersection. As such, impacts to transportation /traffic would be greater at Alternative Site No. 17 as <br />compared to the proposed Project site, and mitigation would not be available to reduce these effects <br />to less than significant levels because there is no way to construct this alternative without impacting <br />travel lanes on South Bristol Street. Furthermore, construction of a lift station at Alternative Site No. <br />17 would exacerbate an existing parking deficiency at this site both during construction and long- <br />term operation. Near- and long -term impacts to parking at Alternative Site No. 17 would be a <br />significant and unmitigable impact. Construction activities at Alternative Site No. 17 also would <br />San Lorenzo Lift Station EIR (Project No. 06 -3510) 3 -37 <br />CEQA Findings of Fact /Statement of Overriding Considerations <br />55A -76 <br />